A and B can finish a work together in 30 days, B and C can finish the same work together in 24 days and A and C can finish the same work together in 40 days. If all three work together, how long will it take them to complete the work?
A और B किसी कार्य को 30 दिनों में समाप्त कर सकते हैं | B और C इसी
कार्य को 24 दिनों में तथा A और C इसी कार्य को एक साथ 40 दिनों में समाप्त कर सकते हैं | यदि ये तीनों साथ कार्य करें, तो उन्हें कार्य समाप्त करने में कितना समय लगेगा ?
20 days
5 days
10 days
15 days
To solve the problem step by step, we need to find out how long it will take for A, B, and C to complete the work together. Here’s how we can do it:
Step 1: Determine the work rates of A, B, and C
Let’s denote the work done by A in one day as A, by B as B, and by C as C.
From the information given:
- A and B can finish the work in 30 days, so their combined work rate is:
A+B=130 (work done per day)
- B and C can finish the work in 24 days, so their combined work rate is:
B+C=124 (work done per day)
- A and C can finish the work in 40 days, so their combined work rate is:
A+C=140 (work done per day)
Step 2: Set up the equations
Now we have three equations:
1. A+B=130
2. B+C=124
3. A+C=140
Step 3: Add all three equations
Adding all three equations together:
(A+B)+(B+C)+(A+C)=130+124+140
This simplifies to:
2A+2B+2C=130+124+140
Step 4: Calculate the right-hand side
To add the fractions, we need to find a common denominator. The LCM of 30, 24, and 40 is 120. Now we convert each fraction:
- 130=4120
- 124=5120
- 140=3120
Now, adding these fractions:
4120+5120+3120=12120=110
Step 5: Solve for A + B + C
Now we have:
2A+2B+2C=110
Dividing everything by 2:
A+B+C=120
Step 6: Find the time taken when A, B, and C work together
The combined work rate of A, B, and C is 120 work done per day. Therefore, the time taken to complete the work when all three work together is the reciprocal of their combined work rate:
Time=1120=20 days
Thus, A, B, and C together will complete the work in 20 days.
Let’s denote the work done by A in one day as A, by B as B, and by C as C.
- A and B can finish the work in 30 days, so their combined work rate is:
A+B=130 (work done per day)
B+C=124 (work done per day)
A+C=140 (work done per day)
Now we have three equations:
1. A+B=130
2. B+C=124
3. A+C=140
Adding all three equations together:
(A+B)+(B+C)+(A+C)=130+124+140
This simplifies to:
2A+2B+2C=130+124+140
To add the fractions, we need to find a common denominator. The LCM of 30, 24, and 40 is 120. Now we convert each fraction:
- 130=4120
- 124=5120
- 140=3120
4120+5120+3120=12120=110
Now we have:
2A+2B+2C=110
Dividing everything by 2:
A+B+C=120
The combined work rate of A, B, and C is 120 work done per day. Therefore, the time taken to complete the work when all three work together is the reciprocal of their combined work rate:
Time=1120=20 days
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 36 days, B and C can do the same work in 60 days. A and C can do the same work in 45 days. In how many days can B alone complete the same work?
A और B एक कार्य 36 दिनों में कर सकते हैं, B और C उसी कार्य को 60 दिनों में कर सकते हैं। A और C उसी कार्य को 45 दिनों में कर सकते हैं। B अकेले कितने दिनों में कार्य पूरा कर सकता है?
View SolutionBoth A and B working together can complete a task in 323 days. C and D complete the same task in 317 days. If A, B, C and D work together, how long will it take to complete half the work?
A और B दोनों मिलकर एक कार्य को 323 दिनों में पूरा करते हैं| C और D उसी कार्य को 317 दिनों में पूरा करते हैं | यदि A, B, C और D एक साथ मिलकर कार्य करते हैं तो आधे कार्य को पूरा करने में उन्हें कितना समय लगेगा ?
View Solution
Knowledge Check
A and B can finish a work together in 323 days. C and D can finish the same work in 317 days. If A, B, C and D do the work together, how long will it take for then to finish half of the work?
A1113 daysB1113 daysC813 daysD213 daysA can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
A11516B21516C31516D41516A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in
A12 daysB14 daysC16 daysD24 days
A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे
View SolutionA and B , working together, can complete a work in 16 days, C and A together can complete it in 32 days and C and B together can complete it in 24 days. They worked together for 12 days. In how many days will C can complete the remaining work ? /
A और B एक साथ कार्य करते हुए किसी कार्य को 16 दिनों में कर सकते हैं, C और A इस कार्य को 32 दिनों में कर सकते हैं और C और A इस कार्य को 32 दिनों में कर सकते हैं | उन्होंने 12 दिनों तक साथ कार्य किया | शेष कार्य समाप्त करने में C को कितने दिन लगेंगे ?
View SolutionA and B can do a piece of work in 36 days, B and C can do the same work in 60 days. A and C can do the same work in 45 days. In how many days can A alone complete the work ?
A और B 36 दिनों में एक कार्य को कर सकते हैं, B और C 60 दिनों में उसी कार्य को कर सकते हैं। A और C उसी कार्य को 45 दिनों में कर सकते हैं। A अकेले कितने दिनों में वह कार्य पूरा कर सकता है?
View SolutionA and B can do a work in 12 days, B and C can do it in 15 days and C and A can do it in 20 days. If A, B and C work together, then they will complete the same work in:
A और B एक कार्य को 12 दिनों में कर सकते हैं, B और C इसे 15 दिनों में कर सकते हैं और C और A इसे 20 दिनों में कर सकते हैं। यदि A, B और C एक साथ कार्य करते हैं, तो वे उसी कार्य को कितने समय में पूरा करेंगे?
View SolutionA can do a piece of work alone in 10 days. A and B together can do the same work in 20/3 days. A, B and C can do the same work together in 40/7 days. In how many days can B and C do the same work together?
A किसी कार्य को अकेले 10 दिन में कर सकता है | A तथा B उसी कार्य को मिलकर 20/3 दिनों में कर सकते हैं |A, B तथा C उसी कार्य को मिलकर 40/7 दिनों में कर सकते हैं | B तथा C उसी कार्य को मिलकर कितने दिनों में कर सकते हैं?
View Solution