A and B can finish a work together in 30 days, B and C can finish the same work together in 24 days and A and C can finish the same work together in 40 days. If all three work together, how long will it take them to complete the work?
A और B किसी कार्य को 30 दिनों में समाप्त कर सकते हैं | B और C इसी कार्य को 24 दिनों में तथा A और C इसी कार्य को एक साथ 40 दिनों में समाप्त कर सकते हैं | यदि ये तीनों साथ कार्य करें, तो उन्हें कार्य समाप्त करने में कितना समय लगेगा ?

A

20 days

B

5 days

C

10 days

D

15 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we need to find out how long it will take for A, B, and C to complete the work together. Here’s how we can do it:

Step 1: Determine the work rates of A, B, and C
Let’s denote the work done by A in one day as A, by B as B, and by C as C.

From the information given:
- A and B can finish the work in 30 days, so their combined work rate is:
A+B=130 (work done per day)

- B and C can finish the work in 24 days, so their combined work rate is:
B+C=124 (work done per day)

- A and C can finish the work in 40 days, so their combined work rate is:
A+C=140 (work done per day)

Step 2: Set up the equations
Now we have three equations:
1. A+B=130
2. B+C=124
3. A+C=140

Step 3: Add all three equations
Adding all three equations together:
(A+B)+(B+C)+(A+C)=130+124+140
This simplifies to:
2A+2B+2C=130+124+140

Step 4: Calculate the right-hand side
To add the fractions, we need to find a common denominator. The LCM of 30, 24, and 40 is 120. Now we convert each fraction:
- 130=4120
- 124=5120
- 140=3120

Now, adding these fractions:
4120+5120+3120=12120=110

Step 5: Solve for A + B + C
Now we have:
2A+2B+2C=110
Dividing everything by 2:
A+B+C=120

Step 6: Find the time taken when A, B, and C work together
The combined work rate of A, B, and C is 120 work done per day. Therefore, the time taken to complete the work when all three work together is the reciprocal of their combined work rate:
Time=1120=20 days

Thus, A, B, and C together will complete the work in 20 days.

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can finish a work together in 323 days. C and D can finish the same work in 317 days. If A, B, C and D do the work together, how long will it take for then to finish half of the work?

    A1113 days
    B1113 days
    C813 days
    D213 days
  • A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.

    A11516
    B21516
    C31516
    D41516
  • A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days