Doubtnut Promotions Sticky

A certain number of persons can complete a work in 34 days working 9 hours a day. If the number of persons is decreased by 40%, then how many hours a day should the remaining persons work to complete the work in 51 days ?
कुछ व्यक्ति किसी कार्य को एक दिन में 9 घंटे कार्य करते हुए 34 दिनों में पूरा कर सकते हैं | यदि व्यक्तियों की संख्या 40% से कम कर दी जाए, तो शेष व्यक्तियों को इस कार्य को 51 दिनों में पूरा करने के लिए दिन में कितने घंटे कार्य करना पड़ेगा ?

A

a)9

B

b)30

C

c)12

D

d)10

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step-by-step, we can follow these steps:

Step 1: Determine the Total Work
Let the number of persons be x. The total work done can be calculated as follows:
Total Work=Number of Persons×Number of Days×Hours per Day
Given that the work is completed in 34 days with 9 hours of work each day, we have:
Total Work=x×34×9

Step 2: Calculate the New Number of Persons
If the number of persons is decreased by 40%, the remaining persons will be:
Remaining Persons=x0.4x=0.6x

Step 3: Set Up the Equation for the New Scenario
In the new scenario, the remaining persons (0.6x) will work for 51 days. Let A be the number of hours they need to work each day. The total work done in this scenario can be expressed as:
Total Work=Remaining Persons×New Number of Days×New Hours per Day
Thus, we have:
Total Work=0.6x×51×A

Step 4: Equate the Total Work from Both Scenarios
Since the total work remains the same in both scenarios, we can set the two equations equal to each other:
x×34×9=0.6x×51×A

Step 5: Simplify the Equation
We can cancel x from both sides (assuming x0):
34×9=0.6×51×A

Step 6: Calculate the Left Side
Calculating the left side:
34×9=306

Step 7: Substitute and Solve for A
Now we substitute into the equation:
306=0.6×51×A
Calculating 0.6×51:
0.6×51=30.6
Now the equation becomes:
306=30.6×A
To find A, we divide both sides by 30.6:
A=30630.6=10

Conclusion
The remaining persons should work 10 hours a day to complete the work in 51 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A certain number of persons can complete a work in 34 days working 9 hours a day. If the number of persons is decreased by 40%, then how many hours a day should the remaining persons work to complete the work in 51 days ?
    कुछ व्यक्ति किसी कार्य को एक दिन में 9 घंटे कार्य करते हुए 34 दिनों में पूरा कर सकते हैं | यदि व्यक्तियों की संख्या 40% से कम कर दी जाए, तो शेष व्यक्तियों को इस कार्य को 51 दिनों में पूरा करने के लिए दिन में कितने घंटे कार्य करना पड़ेगा ?

    A9
    B8
    C12
    D10
  • Question 2 - Select One

    If 30 persons take 10 days to complete a certain work working 8 hours a day. Then 40 persons should work how many hours a day so that the work is completed in 6 days?
    यदि 30 लोग प्रतिदिन 8 घंटे कार्य करके किसी कार्य को 10 दिनों में पूरा करते हैं, तो इस कार्य को 6 दिनों में पूरा करने के लिए 40 व्यक्ति दिन में कितने घंटे कार्य करेंगे ?

    A6
    B10
    C8
    D12
  • Question 3 - Select One

    Working 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day ?

    A42
    B30
    C35
    D36