Doubtnut Promotions Sticky

A can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?

A

10

B

12

C

9

D

15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will analyze the work done by A and B, calculate their individual work rates, and then determine how long it takes to complete the entire work.

Step 1: Determine the work rates of A and B
- A can do 40% of the work in 6 days.
- B can do 30% of the work in 3 days.

Work rate of A:
- 40% = 0.4 of the work in 6 days.
- Therefore, A's work rate = 0.46=230=115 of the work per day.

Work rate of B:
- 30% = 0.3 of the work in 3 days.
- Therefore, B's work rate = 0.33=110 of the work per day.

Step 2: Calculate the combined work rate of A and B
- Combined work rate = A's work rate + B's work rate
- Combined work rate = 115+110

To add these fractions, we need a common denominator:
- The least common multiple of 15 and 10 is 30.

Convert the fractions:
- 115=230
- 110=330

Now add them:
- Combined work rate = 230+330=530=16 of the work per day.

Step 3: Calculate the work done in the first 2 days
- In 2 days, A and B together will complete:
- Work done in 2 days = 2×16=26=13 of the work.

Step 4: Calculate the remaining work
- Total work = 1 (100%)
- Work completed in 2 days = 13
- Remaining work = 113=23

Step 5: Calculate the time taken by A to complete the remaining work
- After 2 days, B leaves, and A continues to work alone.
- A's work rate is 115 of the work per day.
- Time taken by A to complete the remaining 23 of the work:

Time=Remaining Work÷A's Work Rate=2/31/15=23×15=10 days

Step 6: Calculate the total time taken to complete the work
- Total time = Time worked together (2 days) + Time taken by A alone (10 days)
- Total time = 2+10=12 days

Final Answer
The entire work was completed in 12 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions