Doubtnut Promotions Sticky

A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in :
A की कार्य क्षमता B और C की कुल कार्य क्षमता के बराबर है | एक साथ कार्य करते हुए, A और B किसी कार्य को 36 दिनों में कर सकते हैं तथा C अकेले इस कार्य को 60 दिनों में कर सकता है | A और C 10 दिनों तक एक साथ कार्य करते हैं | B अकेले शेष कार्य कितने दिनों में समाप्त करेगा ?

A

110 days

B

88 days

C

84 days

D

90 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the efficiencies of A, B, and C
Given that A is as efficient as B and C together, we can denote:
- Efficiency of C = 160 (since C can complete the work in 60 days)
- Let the efficiency of B be b.
- Since A is as efficient as B and C together, we have:
Efficiency of A=b+160

Step 2: Find the efficiency of A and B together
A and B together can complete the work in 36 days, so their combined efficiency is:
Efficiency of A + B=136
Substituting the efficiency of A from the previous step:
b+(b+160)=136
This simplifies to:
2b+160=136

Step 3: Solve for B's efficiency
To solve for b, first, we need a common denominator for 136 and 160. The least common multiple of 36 and 60 is 180. Thus:
136=5180and160=3180
Now substituting back:
2b+3180=5180
Subtract 3180 from both sides:
2b=51803180=2180=190
Thus,
b=1180

Step 4: Calculate A's efficiency
Now substituting b back to find A's efficiency:
Efficiency of A=b+160=1180+160
Finding a common denominator (which is 180):
160=3180
So,
Efficiency of A=1180+3180=4180=145

Step 5: Calculate work done by A and C in 10 days
Now, A and C work together for 10 days:
Efficiency of A + C=145+160
Finding a common denominator (which is 180):
145=4180and160=3180
So,
Efficiency of A + C=4180+3180=7180
In 10 days, the work done by A and C is:
Work done=Efficiency×Time=7180×10=70180=718

Step 6: Calculate remaining work
The total work is 1 (the whole work), so the remaining work after A and C have worked for 10 days is:
Remaining work=1718=1818718=1118

Step 7: Calculate time taken by B to finish remaining work
B's efficiency is 1180. The time taken by B to complete the remaining work is:
Time=Remaining workEfficiency of B=11181180=1118×180=110 days

Final Answer
B alone will complete the remaining work in 110 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42
  • Question 2 - Select One

    Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42
  • Question 3 - Select One

    A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?

    A80 days
    B84 days
    C84 days
    D92 days