A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in :
A की कार्य क्षमता B और C की कुल कार्य क्षमता के बराबर है | एक साथ कार्य करते हुए, A और B किसी कार्य को 36 दिनों में कर सकते हैं तथा C अकेले इस कार्य को 60 दिनों में कर सकता है | A और C 10 दिनों तक एक साथ कार्य करते हैं | B अकेले शेष कार्य कितने दिनों में समाप्त करेगा ?
110 days
88 days
84 days
90 days
To solve the problem step by step, let's break it down:
Step 1: Determine the efficiencies of A, B, and C
Given that A is as efficient as B and C together, we can denote:
- Efficiency of C = 160 (since C can complete the work in 60 days)
- Let the efficiency of B be b.
- Since A is as efficient as B and C together, we have:
Efficiency of A=b+160
Step 2: Find the efficiency of A and B together
A and B together can complete the work in 36 days, so their combined efficiency is:
Efficiency of A + B=136
Substituting the efficiency of A from the previous step:
b+(b+160)=136
This simplifies to:
2b+160=136
Step 3: Solve for B's efficiency
To solve for b, first, we need a common denominator for 136 and 160. The least common multiple of 36 and 60 is 180. Thus:
136=5180and160=3180
Now substituting back:
2b+3180=5180
Subtract 3180 from both sides:
2b=5180−3180=2180=190
Thus,
b=1180
Step 4: Calculate A's efficiency
Now substituting b back to find A's efficiency:
Efficiency of A=b+160=1180+160
Finding a common denominator (which is 180):
160=3180
So,
Efficiency of A=1180+3180=4180=145
Step 5: Calculate work done by A and C in 10 days
Now, A and C work together for 10 days:
Efficiency of A + C=145+160
Finding a common denominator (which is 180):
145=4180and160=3180
So,
Efficiency of A + C=4180+3180=7180
In 10 days, the work done by A and C is:
Work done=Efficiency×Time=7180×10=70180=718
Step 6: Calculate remaining work
The total work is 1 (the whole work), so the remaining work after A and C have worked for 10 days is:
Remaining work=1−718=1818−718=1118
Step 7: Calculate time taken by B to finish remaining work
B's efficiency is 1180. The time taken by B to complete the remaining work is:
Time=Remaining workEfficiency of B=11181180=1118×180=110 days
Final Answer
B alone will complete the remaining work in 110 days.
---
Given that A is as efficient as B and C together, we can denote:
- Efficiency of C = 160 (since C can complete the work in 60 days)
- Let the efficiency of B be b.
- Since A is as efficient as B and C together, we have:
Efficiency of A=b+160
A and B together can complete the work in 36 days, so their combined efficiency is:
Efficiency of A + B=136
Substituting the efficiency of A from the previous step:
b+(b+160)=136
This simplifies to:
2b+160=136
To solve for b, first, we need a common denominator for 136 and 160. The least common multiple of 36 and 60 is 180. Thus:
136=5180and160=3180
Now substituting back:
2b+3180=5180
Subtract 3180 from both sides:
2b=5180−3180=2180=190
Thus,
b=1180
Now substituting b back to find A's efficiency:
Efficiency of A=b+160=1180+160
Finding a common denominator (which is 180):
160=3180
So,
Efficiency of A=1180+3180=4180=145
Now, A and C work together for 10 days:
Efficiency of A + C=145+160
Finding a common denominator (which is 180):
145=4180and160=3180
So,
Efficiency of A + C=4180+3180=7180
In 10 days, the work done by A and C is:
Work done=Efficiency×Time=7180×10=70180=718
The total work is 1 (the whole work), so the remaining work after A and C have worked for 10 days is:
Remaining work=1−718=1818−718=1118
B's efficiency is 1180. The time taken by B to complete the remaining work is:
Time=Remaining workEfficiency of B=11181180=1118×180=110 days
B alone will complete the remaining work in 110 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
A80 daysB84 daysC84 daysD92 days
A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
View SolutionA is twice as efficient as B and B is thrice as efficient as C. Working together, they can finish a certain work in 5 days. If A and C worked together for 5 days then B alone would complete the remaining work in .......
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे
View SolutionA alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
View Solution