Doubtnut Promotions Sticky

A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
A किसी कार्य का 40% भाग 12 दिनों में कर सकता है जबकि B इसी कार्य का 60% भाग 15 दिनों में कर सकता है |दोनों 10 दिनों तक एक साथ कार्य करते हैं | C शेष कार्य 4 दिनों में पूरा करता है | A, B और C एक साथ इसी कार्य का 28% भाग कितने दिनों में पूरा करेंगे ?

A

2 1 2 days

B

3 days

C

1 1 2 days

D

2 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the total work in terms of units
A can do 40% of the work in 12 days. Therefore, to find out how long it would take A to complete 100% of the work:
- If 40% is done in 12 days, then 100% would be done in:
Total days for A=12 days0.4=30 days

B can do 60% of the work in 15 days. Therefore, to find out how long it would take B to complete 100% of the work:
- If 60% is done in 15 days, then 100% would be done in:
Total days for B=15 days0.6=25 days

Step 2: Calculate the total work in units
Assuming the total work is 150 units (the LCM of 30 and 25):
- A's work rate (efficiency) is:
A's efficiency=150 units30 days=5 units/day
- B's work rate (efficiency) is:
B's efficiency=150 units25 days=6 units/day

Step 3: Calculate how much work A and B do together in 10 days
- Combined efficiency of A and B:
Combined efficiency=5+6=11 units/day
- Work done by A and B in 10 days:
Work done=11 units/day×10 days=110 units

Step 4: Calculate the remaining work
- Total work is 150 units, and A and B have completed 110 units:
Remaining work=150110=40 units

Step 5: Determine C's efficiency
C completes the remaining 40 units of work in 4 days:
- C's efficiency is:
C's efficiency=40 units4 days=10 units/day

Step 6: Calculate the combined efficiency of A, B, and C
- Combined efficiency of A, B, and C:
Combined efficiency=5+6+10=21 units/day

Step 7: Calculate the time taken by A, B, and C to complete 28% of the work
- 28% of the total work (150 units):
Work to be completed=0.28×150=42 units
- Time taken to complete 42 units with a combined efficiency of 21 units/day:
Time=42 units21 units/day=2 days

Final Answer
A, B, and C together will complete 28% of the work in 2 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • Question 2 - Select One

    A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days
  • Question 3 - Select One

    A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days