Doubtnut Promotions Sticky

A can do one-third of a work in 15 days, B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work ?
A किसी कार्य का एक-तिहाई भाग 15 दिनों में पूरा कर सकता है |B इसी कार्य का 75% भाग 18 दिनों में तथा C यही कार्य 36 दिनों में कर सकता है | B और C 8 दिनों तक साथ कार्य करते हैं | A अकेला शेष कार्य कितने दिनों में पूरा करेगा ?

A

24 days

B

18 days

C

20 days

D

16 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the total work done by A, B, and C, and then calculate how long A will take to finish the remaining work after B and C have worked together for 8 days.

Step 1: Determine the total work done by A, B, and C

1. Calculate the total time taken by A to complete the work:
- A can do one-third of the work in 15 days.
- Therefore, the total work will take 3×15=45 days.

2. Calculate the total time taken by B to complete the work:
- B can do 75% of the work in 18 days.
- To find the total time taken by B for 100% of the work, we use the formula:
Total time for B=18 days×10075=24 days

3. Total time taken by C to complete the work:
- C can complete the work in 36 days.

Step 2: Calculate the efficiency of A, B, and C

1. Total work (in terms of LCM):
- We find the LCM of the total days taken by A, B, and C: LCM(45, 24, 36) = 360.

2. Calculate the efficiency of each worker:
- Efficiency of A:
Efficiency of A=36045=8
- Efficiency of B:
Efficiency of B=36024=15
- Efficiency of C:
Efficiency of C=36036=10

Step 3: Calculate the work done by B and C together in 8 days

1. Total efficiency of B and C:
Total efficiency of B and C=15+10=25

2. Total work done by B and C in 8 days:
Work done=25×8=200

Step 4: Calculate the remaining work

1. Remaining work:
Remaining work=360200=160

Step 5: Calculate the time taken by A to complete the remaining work

1. Time taken by A to complete the remaining work:
Time=Remaining workEfficiency of A=1608=20 days

Final Answer
A will take 20 days to complete the remaining work alone.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

    A5
    B512
    C6
    D8
  • Question 2 - Select One

    A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?

    A120 days
    B118 days
    C115 days
    D110 days
  • Question 3 - Select One

    A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days