Doubtnut Promotions Sticky

The ratio of the amount of work done by (x-1) labours in (x+1) days and that done by (x+1) labours in (x+2) days is 5:6. Then the value of x is

A

1. 16

B

2. 15

C

3. 17

D

4. 14

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to find the value of x given the ratio of work done by two groups of laborers. Let's break it down step by step.

Step 1: Define the Work Done
Let:
- m1=x1 (number of labors in the first group)
- d1=x+1 (number of days worked by the first group)
- m2=x+1 (number of labors in the second group)
- d2=x+2 (number of days worked by the second group)

Step 2: Calculate the Work Done by Each Group
The work done by the first group W1 can be calculated as:
W1=m1×d1=(x1)(x+1)

The work done by the second group W2 can be calculated as:
W2=m2×d2=(x+1)(x+2)

Step 3: Set Up the Ratio
According to the problem, the ratio of the work done by the two groups is given as:
W1W2=56

Step 4: Substitute the Work Done into the Ratio
Substituting W1 and W2 into the ratio gives us:
(x1)(x+1)(x+1)(x+2)=56

Step 5: Cross Multiply to Eliminate the Fraction
Cross multiplying gives us:
6(x1)(x+1)=5(x+1)(x+2)

Step 6: Expand Both Sides
Expanding both sides:
- Left side:
6(x21)=6x26
- Right side:
5(x2+3x+2)=5x2+15x+10

Step 7: Set the Equation to Zero
Setting the equation to zero:
6x26=5x2+15x+10
Rearranging gives:
6x25x215x610=0
x215x16=0

Step 8: Factor the Quadratic Equation
We can factor the quadratic equation:
(x16)(x+1)=0

Step 9: Solve for x
Setting each factor to zero gives us:
1. x16=0x=16
2. x+1=0x=1 (not a valid solution since x must be positive)

Thus, the only valid solution is:
x=16

Final Answer
The value of x is 16.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Work done by (x+4) men in (x+5) days is equal to the work done by (x-5) men in (x+20) days. What is the value of x?

    A20
    B25
    C30
    D15
  • Question 2 - Select One

    If the work done by (x-1) men in (x + 1) days is to the work done by (x + 2) men in (x - 1) days are in the ratio 9:10, then the value of x is equal to :

    A5
    B6
    C7
    D8
  • Question 3 - Select One

    If the work done by (x – 1) men in (x + 1) days and the work done by (x + 2) men in (x – 1) days is in the ratio of 9 : 10, then x is equal to .

    A5
    B6
    C7
    D8