If 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.
1. 58
2. 13
3. 79
4. 23
The correct Answer is:C
To solve the problem step by step, we will use the concept of work done, which can be calculated using the formula:
Work=Number of Men×Number of Days×Number of Hours per Day
Step 1: Calculate the total work done by 90 men in 16 days working 12 hours a day.
Using the formula:
W1=M1×D1×H1
Where:
- M1=90 (men)
- D1=16 (days)
- H1=12 (hours/day)
Substituting the values:
W1=90×16×12
Calculating:
W1=90×16=1440
W1=1440×12=17280 man-hours
Step 2: Calculate the total work done by 70 men in 24 days working 8 hours a day.
Using the same formula:
W2=M2×D2×H2
Where:
- M2=70 (men)
- D2=24 (days)
- H2=8 (hours/day)
Substituting the values:
W2=70×24×8
Calculating:
W2=70×24=1680
W2=1680×8=13440 man-hours
Step 3: Calculate the part of work completed by 70 men in 24 days working 8 hours a day compared to the total work done by 90 men in 16 days.
To find the part of the work completed by the second group of men compared to the total work done by the first group, we can take the ratio:
Part of work=W2W1
Substituting the values we calculated:
Part of work=1344017280
Simplifying the fraction:
Part of work=13440÷1344017280÷13440=11.2857≈79
Final Answer:
The part of the work which can be completed by 70 men in 24 days working 8 hours a day is 79 of the total work.
---
- M1=90 (men)
- D1=16 (days)
- H1=12 (hours/day)
W1=1440×12=17280 man-hours
- M2=70 (men)
- D2=24 (days)
- H2=8 (hours/day)
W2=1680×8=13440 man-hours
The part of the work which can be completed by 70 men in 24 days working 8 hours a day is 79 of the total work.
Topper's Solved these Questions
Similar Questions
If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionA piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?
View Solution
Knowledge Check
- Question 1 - Select One
If 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.
A13B23C79D58 - Question 2 - Select One
If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?
Aa) 15Bb) 12Cc) 10Dd) 16 - Question 3 - Select One
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?
AA. 16BB. 15CC. 10DD. 12
12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionA piece of work can be done by 16 man in 8 days working 12 hours a day. How many men ar needed to complete another work,which is three times the first one, in 24n days working 8 hourse, a day?
View SolutionIf 3 men or 6 boy, can do a piece of work in 10 days, working 7 hours a day; how many days will it take to complete a piece of work twice as large with 6 men and 2 boy. 1% 'irking together for 8 hours a day? 6 b. 9 c. 812 d. 712
View Solution