A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in two-third the time. How many workers were there in the group?
2
3
5
11
The correct Answer is:B
To solve the problem step by step, let's denote the number of workers in the group as n.
Step 1: Understanding the Work Done
Assume the total work to be completed is 1 unit. If no workers were withdrawn, the group would finish the job in T days. According to the problem, if no workers were withdrawn, they would finish the job in two-thirds of the time. Thus, the time taken with all workers is:
T=32×(Time taken with workers being withdrawn)
Step 2: Work Done Each Day
On the first day, all n workers work. On the second day, n−1 workers work, on the third day n−2 workers work, and so on, until the last worker is withdrawn on the last day.
Step 3: Total Work Calculation
The total work done can be expressed as:
Total Work=n+(n−1)+(n−2)+…+1
This is the sum of the first n natural numbers, which can be calculated using the formula:
Total Work=n(n+1)2
Step 4: Relating Work to Time
Since the total work is equal to 1 unit, we have:
n(n+1)2=1
Multiplying both sides by 2 gives:
n(n+1)=2
Step 5: Solving the Quadratic Equation
Rearranging the equation gives:
n2+n−2=0
We can factor this quadratic equation:
(n−1)(n+2)=0
Thus, the solutions for n are:
n=1orn=−2
Since n must be a positive integer, we have:
n=1
Step 6: Verification
If there was only 1 worker, the job would take 1 day. If no worker was withdrawn, it would still take 1 day, which is indeed two-thirds of the time taken with workers being withdrawn.
Conclusion
Thus, the number of workers in the group is:
3
Assume the total work to be completed is 1 unit. If no workers were withdrawn, the group would finish the job in T days. According to the problem, if no workers were withdrawn, they would finish the job in two-thirds of the time. Thus, the time taken with all workers is:
On the first day, all n workers work. On the second day, n−1 workers work, on the third day n−2 workers work, and so on, until the last worker is withdrawn on the last day.
The total work done can be expressed as:
Since the total work is equal to 1 unit, we have:
Rearranging the equation gives:
If there was only 1 worker, the job would take 1 day. If no worker was withdrawn, it would still take 1 day, which is indeed two-thirds of the time taken with workers being withdrawn.
Thus, the number of workers in the group is:
Topper's Solved these Questions
Similar Questions
The company divided 15,484 workers equally into 98 groups. How many workers were there in each group?
View Solution10000 workers were employed to construct a river bridge in four years. At the end of first year, 10% workers were retrenched. At the end of the second year, 5% of the workers at the begining of the second year were retrenched. However to complete the project in time, the number of workers was increased by 10% at the end of the third year. How many workers were working during the fourth year ?
View Solution
Knowledge Check
- Question 1 - Select One
A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group?
A50B40C45D10 - Question 2 - Select One
A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in two-third the time. How many workers were there in the group?
A50B40C45D10 - Question 3 - Select One
A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less. What was the actual strength of workers?
A30 workersB40 workersC42 workersD36 workers
10000 workers were employed to construct a river bridge In four years. At the end of first year, 10% workers were retrenched. At the end of the second year, 5% of the workers at that time were retrenched. However to complete the project in time, the number of workers was increased by 10% at the end of the third year. How many workers were working during the fourth year?
View SolutionA group of workers having equal efficiency can complete a job in 4 days. But it so happened that every alternate day starting from the second day, 3 workers are withdrawn from the job and every alternate day starting from the third day, 2 workers are added to the group. If it now takes 7 days to complete the job, find the number of workers who started the job. 4 b. 5 c. 6 d. 8
View SolutionA group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?
View Solution100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
View SolutionA group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
View Solution