Doubtnut Promotions Sticky

35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

A

20

B

35

C

30

D

25

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for 35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?

    A12 days
    B7 days
    C9 days
    DNone of these
  • Question 2 - Select One

    25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?

    A120
    B125
    C100
    D215
  • Question 3 - Select One

    A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

    A25
    B50
    C75
    Dcan't be determined