35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is
20
35
30
25
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Determine the total amount of work
We know that 35 persons are engaged to complete the work in 60 days. Therefore, the total work can be expressed in terms of "man-days".
Total work = Number of persons × Number of days
Total work = 35 persons × 60 days = 2100 man-days
Hint: Remember that "man-days" is a way to express the total work done by a certain number of people over a certain number of days.
Step 2: Calculate the work done in 32 days
After 32 days, it is observed that 25 of the work has been completed.
Work done = 25 of Total work
Work done = 25 × 2100 man-days = 840 man-days
Hint: To find the work done, multiply the fraction of work completed by the total work.
Step 3: Calculate the remaining work
To find the remaining work, we subtract the work done from the total work.
Remaining work = Total work - Work done
Remaining work = 2100 man-days - 840 man-days = 1260 man-days
Hint: The remaining work is simply the total work minus the work that has already been completed.
Step 4: Determine the remaining time
The total time given for the work is 60 days, and 32 days have already passed.
Remaining time = Total time - Time passed
Remaining time = 60 days - 32 days = 28 days
Hint: Subtract the time already spent from the total time to find out how much time is left.
Step 5: Calculate the number of persons needed to complete the remaining work
Now, we need to find out how many persons are required to complete the remaining work in the remaining time.
Let x be the number of persons required.
We can set up the equation:
Remaining work = Number of persons × Remaining time
1260 man-days = x persons × 28 days
Now, solving for x:
x=1260 man-days28 days
x=45 persons
Hint: To find the number of persons needed, divide the remaining work by the remaining time.
Step 6: Calculate the additional persons needed
Since there are already 35 persons working, we need to find out how many additional persons are required.
Additional persons needed = Total persons required - Persons already working
Additional persons needed = 45 persons - 35 persons = 10 persons
Hint: To find the additional number of persons required, subtract the current number of workers from the total number needed.
Final Answer
The number of persons to be engaged to complete the remaining work in the said period is 10 persons.
We know that 35 persons are engaged to complete the work in 60 days. Therefore, the total work can be expressed in terms of "man-days".
Total work = 35 persons × 60 days = 2100 man-days
After 32 days, it is observed that 25 of the work has been completed.
Work done = 25 × 2100 man-days = 840 man-days
To find the remaining work, we subtract the work done from the total work.
Remaining work = 2100 man-days - 840 man-days = 1260 man-days
The total time given for the work is 60 days, and 32 days have already passed.
Remaining time = 60 days - 32 days = 28 days
Now, we need to find out how many persons are required to complete the remaining work in the remaining time.
Remaining work = Number of persons × Remaining time
1260 man-days = x persons × 28 days
x=1260 man-days28 days
x=45 persons
Since there are already 35 persons working, we need to find out how many additional persons are required.
Additional persons needed = 45 persons - 35 persons = 10 persons
The number of persons to be engaged to complete the remaining work in the said period is 10 persons.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
A12 daysB7 daysC9 daysDNone of these - Question 2 - Select One
25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
A120B125C100D215 - Question 3 - Select One
A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
A25B50C75Dcan't be determined
If 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionIf 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View SolutionIf 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solution