If 7 men working 7 hrs a day for each of 7 days produce 7 units of work, then the units of work produced by 5 men working 5 hrs a day for each of 5 days is 25
25343
12549
49125
34325
The correct Answer is:B
To solve the problem, we will use the relationship between the number of men, the number of days, the number of hours, and the amount of work done.
1. Identify the Given Information:
- In the first scenario:
- Number of men (M1) = 7
- Number of days (D1) = 7
- Number of hours per day (H1) = 7
- Work done (W1) = 7 units
- In the second scenario:
- Number of men (M2) = 5
- Number of days (D2) = 5
- Number of hours per day (H2) = 5
- Work done (W2) = ?
2. Set Up the Work Formula:
The formula relating the work done is:
M1×D1×H1W1=M2×D2×H2W2
3. Substitute the Known Values:
Substitute the values from the first scenario into the formula:
7×7×77=5×5×5W2
4. Simplify the Left Side:
Calculate the left side:
7×7×77=7×7=49
5. Set Up the Equation:
Now we have:
49=5×5×5W2
6. Calculate the Right Side:
Calculate 5×5×5:
5×5×5=125
7. Set Up the Final Equation:
Now we have:
49=125W2
8. Cross-Multiply to Solve for W2:
Cross-multiply to find W2:
49×W2=125
W2=12549
9. Final Answer:
Thus, the units of work produced by 5 men working 5 hours a day for 5 days is:
W2=12549 units
- In the first scenario:
- Number of men (M1) = 7
- Number of days (D1) = 7
- Number of hours per day (H1) = 7
- Work done (W1) = 7 units
- In the second scenario:
- Number of men (M2) = 5
- Number of days (D2) = 5
- Number of hours per day (H2) = 5
- Work done (W2) = ?
The formula relating the work done is:
M1×D1×H1W1=M2×D2×H2W2
Substitute the values from the first scenario into the formula:
7×7×77=5×5×5W2
Calculate the left side:
7×7×77=7×7=49
Now we have:
49=5×5×5W2
Calculate 5×5×5:
5×5×5=125
Now we have:
49=125W2
Cross-multiply to find W2:
49×W2=125
W2=12549
Thus, the units of work produced by 5 men working 5 hours a day for 5 days is:
W2=12549 units
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
If 4 men working 4 hours per day for 4 days complete 4.units of work, then how many units of work will be completed by 2 men working for 2 hours per day in 2 days ?
View SolutionIf x men working x hours per day can do x units of work in x days, then y men working y hours per day in y days would be able to do k units of work. What is the value of k ?
View Solution
Knowledge Check
- Question 1 - Select One
If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for n days is
Ap2n2Bp3n2Cn2p2Dn3p2 - Question 2 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15 5/21 daysB11 2/3 daysC6 9/16 daysD4 1/5 days
If 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212
View SolutionIf x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
View SolutionIf m men working m hr per day, can do m units of work in m days, then n men working n hr per day would be able to complete how many units of work in n days?
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View SolutionA person invests money in two different schemes for 5 years and 8 years at 12% and 10% simple interest, respectively. At the completion of each scheme he gets the same interest. The ratio of his investments is
View Solution