Doubtnut Promotions Sticky

Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

A

10

B

21

C

15

D

18

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to find the original number of men who promised to complete the work in 10 days. Let's break it down step by step.

Step 1: Define the Variables
Let the original number of men be x.

Step 2: Calculate the Total Work
The total work can be calculated based on the number of men and the number of days they promised to work. If x men can complete the work in 10 days, the total work (in man-days) is:
Total Work=x×10

Step 3: Calculate Work Done by Remaining Men
Since 8 men were absent, the number of men who actually worked is x8. These remaining men completed the work in 18 days. Therefore, the total work done by these men is:
Total Work=(x8)×18

Step 4: Set the Equations Equal
Since both expressions represent the same total work, we can set them equal to each other:
x×10=(x8)×18

Step 5: Expand the Equation
Expanding the right side gives us:
10x=18x144

Step 6: Rearrange the Equation
Now, we will rearrange the equation to isolate x:
10x18x=144
8x=144

Step 7: Solve for x
Dividing both sides by -8 gives:
x=1448=18

Conclusion
The original number of men is 18.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

    A10
    B21
    C15
    D18
  • Question 2 - Select One

    Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

    A10
    B15
    C12
    D14
  • Question 3 - Select One

    Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

    A24
    B20
    C16
    D18