Doubtnut Promotions Sticky

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?

A

40

B

50

C

48

D

56

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D


64 दिनों में पूण किया गया काम = 23
माना प्रत्येक आदमी की क्षमता x है। 120x × 64 = 23
x=23×120×64=(13×120×32)
शेष दिन = 124-64 = 60
शेष दिन = 1-23 = (13)
माना y आदमी को हटाया गया (120y)×13×120×32)×60=13
120 y = 120 -64 = 56 दिन

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?

    A48
    B56
    C40
    D50
  • Question 2 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
    How many men can be discharged now so that the work may finish in time?

    A48
    B56
    C40
    D50
  • Question 3 - Select One

    A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :

    A45
    B40
    C35
    D30