Doubtnut Promotions Sticky

6 men complete a piece of work in 12 days. 8 women can complete the same piece of work in 18 days. Whereas 18 children can complete the piece of work in 10 days. 4 men, 12 women and 20 children work together for 2 days, and then only 36 men were to complete the remaining work in x day.
56x soldiers can complete a piece of work in 24 days. In how many days can 42 soldiers complete the same piece of work?

A

32 days

B

24 days

C

16 days

D

48 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's break it down into manageable parts.

Step 1: Calculate the total work in terms of efficiency

1. Men's Efficiency:
- 6 men complete the work in 12 days.
- Total work = Efficiency × Time = 6m × 12 = 72m (where m is the efficiency of one man).

2. Women's Efficiency:
- 8 women complete the work in 18 days.
- Total work = 8w × 18 = 144w (where w is the efficiency of one woman).

3. Children's Efficiency:
- 18 children complete the work in 10 days.
- Total work = 18c × 10 = 180c (where c is the efficiency of one child).

Since the total work is the same, we can set these equations equal to each other:

72m=144w=180c

Step 2: Establish the ratio of efficiencies

From the equations above, we can express the efficiencies in terms of a common variable:

1. From 72m=144w:
m=2w

2. From 72m=180c:
m=54c

Now we can express everything in terms of c:

- From m=54c, we can substitute into m=2w:
2w=54c
w=58c

Now we have:
- m=54c
- w=58c

Step 3: Calculate the total work done by 4 men, 12 women, and 20 children in 2 days

1. Work done by 4 men in 2 days:
Work by 4 men=4m×2=8m

2. Work done by 12 women in 2 days:
Work by 12 women=12w×2=24w

3. Work done by 20 children in 2 days:
Work by 20 children=20c×2=40c

Now substituting m and w in terms of c:

- Work by 4 men:
8m=8×54c=10c

- Work by 12 women:
24w=24×58c=15c

- Work by 20 children:
40c=40c

Total work done in 2 days:
Total work=10c+15c+40c=65c

Step 4: Calculate remaining work

Total work (from earlier) is 720 (using 72m).

Remaining work after 2 days:
Remaining work=72065c

Step 5: Calculate the efficiency of 36 men

Efficiency of 36 men:
Efficiency=36m=36×54c=45c

Step 6: Calculate the time x for 36 men to complete the remaining work

Using the formula:
Remaining work=Efficiency×Time
72065c=45c×x

Rearranging gives:
72065c=45cx
720=45cx+65c
720=c(45x+65)

Step 7: Calculate the value of c

From the total work:
720=180c
c=4

Step 8: Substitute c back to find x

Substituting c:
720=4(45x+65)
720=180x+260
460=180x
x=460180=239

Step 9: Calculate how many days 42 soldiers can complete the work

Given that 56 soldiers can complete the work in 24 days:
Total work=56×24=1344

Now, we need to find how many days d it takes for 42 soldiers to complete the same work:
1344=42d
d=134442=32

Final Answer
Thus, 42 soldiers can complete the work in 32 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?

    A6days
    B5days
    C4days
    D7days
  • Question 2 - Select One

    12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

    A60 days
    B45 days
    C54 days
    D48 days
  • Question 3 - Select One

    4 man can complete a piece of work in 2 days. 4 wonen can
    complete the same piece of work in 4 days whereas 5 children
    can complete the same piece of work in 4 days. If, 2 men, 4
    women and 10 children work together, in how many days
    can the work be completed ?

    A1 day
    B3 days
    C2 days
    D4 days