Doubtnut Promotions Sticky

Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
E and F together work for 12 days, then they are replaced by A and B and they completed the remaining work in 10 days. If the ratio of efficiencies of E and F is 3 : 2 and E and F together completed the whole work then find the difference between the part of work done by E and the part of work done by F in one day?

A

A)1200

B

B)1150

C

C)1300

D

D)175

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work. E and F together work for 12 days, then they are replaced by A and B and they completed the remaining work in 10 days. If the ratio of efficiencies of E and F is 3 : 2 and E and F together completed the whole work then find the difference between the part of work done by E and the part of work done by F in one day? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    B is 20% more efficient than A. B started the work & do it for
    x days. And then B is replaced by A, A completed the
    remaining work in x+8 days. Ratio of work done by A & B is
    3:2 IN how many days A & B working together complete
    the whole work?

    A131117days
    B12711days
    C13711days
    D12813days
  • Question 2 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A6623
    B3313
    C1623
    D1427
  • Question 3 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A66(2/3)
    B33(1/3)
    C16(2/3)
    D14(2/7)