Doubtnut Promotions Sticky

A contractor took a construction work for Rs.400000 and employed 50 men to complete the work in 20 days. He decided to set aside 25% of the amount as profit for himself and distributed rest of the amounts among the workers as their wages. But at the end of 18th day, he noticed that the work is behind the schedule. So he employed some women along with the men and decided to pay a woman 80% of what was paid to a man per day. The work was completed 3 days later than the schedule. If the contractor finally had a profit of Rs.31000 only, then how many women were employed by him?

A

A)25

B

B)20

C

C)15

D

D)10

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for A contractor took a construction work for Rs.400000 and employed 50 men to complete the work in 20 days. He decided to set aside 25% of the amount as profit for himself and distributed rest of the amounts among the workers as their wages. But at the end of 18^(th) day, he noticed that the work is behind the schedule. So he employed some women along with the men and decided to pay a woman 80% of what was paid to a man per day. The work was completed 3 days later than the schedule. If the contractor finally had a profit of Rs.31000 only, then how many women were employed by him? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?

    A10
    B12
    C15
    D20
  • Question 2 - Select One

    40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?

    A12
    B20
    C18
    D24
  • Question 3 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?

    A48
    B56
    C40
    D50