A contractor took a construction work for Rs.400000 and employed 50 men to complete the work in 20 days. He decided to set aside 25% of the amount as profit for himself and distributed rest of the amounts among the workers as their wages. But at the end of 18th day, he noticed that the work is behind the schedule. So he employed some women along with the men and decided to pay a woman 80% of what was paid to a man per day. The work was completed 3 days later than the schedule. If the contractor finally had a profit of Rs.31000 only, then how many women were employed by him?
A)25
B)20
C)15
D)10
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Calculate the total amount set aside for wages
The contractor took a total of Rs. 400,000 for the construction work. He decided to set aside 25% of this amount as profit for himself.
Calculation:
- Profit = 25% of 400,000 = 25100×400,000=100,000
- Amount available for wages = Total amount - Profit = 400,000 - 100,000 = Rs. 300,000
Hint: Remember to calculate the percentage of the total amount to find out how much is allocated for wages.
Step 2: Determine the daily wage cost for the men
The contractor employed 50 men to complete the work in 20 days.
Calculation:
- Total wage for 20 days = Rs. 300,000
- Daily wage cost for 50 men = 300,00020=15,000
- Daily wage per man = 15,00050=300
Hint: Divide the total wages by the number of days to find the daily wage, then divide by the number of workers to find the wage per worker.
Step 3: Calculate the total work done in 18 days
In 18 days, the work done is less than expected. We need to calculate how much work was completed in this time.
Calculation:
- Work done in 18 days = Daily wage cost for 50 men × 18 days = 15,000 × 18 = Rs. 270,000
Hint: Multiply the daily wage cost by the number of days worked to find the total expenditure on labor.
Step 4: Determine the remaining amount for the last 5 days
The contractor has 3 days left to complete the work after the 18th day, but he actually completed the work 3 days later, totaling 23 days.
Calculation:
- Total amount spent on labor after 23 days = Rs. 300,000 (total wages)
- Amount spent on labor for the first 18 days = Rs. 270,000
- Remaining amount for the last 5 days = Rs. 300,000 - Rs. 270,000 = Rs. 30,000
Hint: Subtract the amount already spent from the total wages to find out how much is left for the additional labor.
Step 5: Calculate the cost of employing women
Let the number of women employed be W. Each woman is paid 80% of what a man earns.
Calculation:
- Daily wage per woman = 80% of Rs. 300 = Rs. 240
- Total cost for W women for 5 days = W×240×5=1200W
Hint: Remember to calculate the wage for women based on the percentage of men's wages.
Step 6: Set up the equation
The total expenditure for 23 days must equal the total wages available for workers.
Equation:
- Total expenditure = Expenditure for men for 23 days + Expenditure for women for 5 days
- 270,000+1200W=300,000
Step 7: Solve for W
Rearranging the equation gives:
- 1200W=300,000−270,000
- 1200W=30,000
- W=30,0001200=25
Hint: Isolate W by moving all other terms to the other side of the equation.
Final Answer
The contractor employed 25 women to help complete the work.
The contractor took a total of Rs. 400,000 for the construction work. He decided to set aside 25% of this amount as profit for himself.
- Profit = 25% of 400,000 = 25100×400,000=100,000
- Amount available for wages = Total amount - Profit = 400,000 - 100,000 = Rs. 300,000
The contractor employed 50 men to complete the work in 20 days.
- Total wage for 20 days = Rs. 300,000
- Daily wage cost for 50 men = 300,00020=15,000
- Daily wage per man = 15,00050=300
In 18 days, the work done is less than expected. We need to calculate how much work was completed in this time.
- Work done in 18 days = Daily wage cost for 50 men × 18 days = 15,000 × 18 = Rs. 270,000
The contractor has 3 days left to complete the work after the 18th day, but he actually completed the work 3 days later, totaling 23 days.
- Total amount spent on labor after 23 days = Rs. 300,000 (total wages)
- Amount spent on labor for the first 18 days = Rs. 270,000
- Remaining amount for the last 5 days = Rs. 300,000 - Rs. 270,000 = Rs. 30,000
Let the number of women employed be W. Each woman is paid 80% of what a man earns.
- Daily wage per woman = 80% of Rs. 300 = Rs. 240
- Total cost for W women for 5 days = W×240×5=1200W
The total expenditure for 23 days must equal the total wages available for workers.
- Total expenditure = Expenditure for men for 23 days + Expenditure for women for 5 days
- 270,000+1200W=300,000
Rearranging the equation gives:
- 1200W=300,000−270,000
- 1200W=30,000
- W=30,0001200=25
The contractor employed 25 women to help complete the work.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the If the amount of work is also increased by 20% of the actual work, then how many extra days are required (m comparison with scheduled time) but the number of men remained constant
View Solution
Knowledge Check
- Question 1 - Select One
20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
A10B12C15D20 - Question 2 - Select One
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24 - Question 3 - Select One
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
A48B56C40D50
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View Solution20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution