A contractor took a construction work for Rs.400000 and employed 50 men to complete the work in 20 days. He decided to set aside 25% of the amount as profit for himself and distributed rest of the amounts among the workers as their wages. But at the end of 18th day, he noticed that the work is behind the schedule. So he employed some women along with the men and decided to pay a woman 80% of what was paid to a man per day. The work was completed 3 days later than the schedule. If the contractor finally had a profit of Rs.31000 only, then how many women were employed by him?
A)25
B)20
C)15
D)10
The correct Answer is:B
Step by step video, text & image solution for A contractor took a construction work for Rs.400000 and employed 50 men to complete the work in 20 days. He decided to set aside 25% of the amount as profit for himself and distributed rest of the amounts among the workers as their wages. But at the end of 18^(th) day, he noticed that the work is behind the schedule. So he employed some women along with the men and decided to pay a woman 80% of what was paid to a man per day. The work was completed 3 days later than the schedule. If the contractor finally had a profit of Rs.31000 only, then how many women were employed by him? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the If the amount of work is also increased by 20% of the actual work, then how many extra days are required (m comparison with scheduled time) but the number of men remained constant
View Solution
Knowledge Check
- Question 1 - Select One
20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
A10B12C15D20 - Question 2 - Select One
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24 - Question 3 - Select One
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
A48B56C40D50
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View Solution20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution