Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
In how many days, A alone can complete twice the work?
25 days
30 days
40 days
50 days
The correct Answer is:D
Step by step video, text & image solution for Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work. In how many days, A alone can complete twice the work? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A and C started doing a work . After working for 6 days , both left and B alone completed the remaining work in 4 days .In how many days can C alone complete a work in 2 days , then in how many days can A alone complete the work ?
View SolutionA can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View Solution
Knowledge Check
- Question 1 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A6623B3313C1623D1427 - Question 2 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A66(2/3)B33(1/3)C16(2/3)D14(2/7) - Question 3 - Select One
A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
A10B12C15D16
A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View SolutionA started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?
View SolutionA, B and C together can do a piece of work in 40 days. After working with B and C for 16 days, A leaves and then B and C complete the remaining work in 40 days more. A alone could do the work in
View SolutionB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
View SolutionA can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
View Solution