Doubtnut Promotions Sticky

Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
In how many days, A alone can complete twice the work?

A

25 days

B

30 days

C

40 days

D

50 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work. In how many days, A alone can complete twice the work? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A6623
    B3313
    C1623
    D1427
  • Question 2 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A66(2/3)
    B33(1/3)
    C16(2/3)
    D14(2/7)
  • Question 3 - Select One

    A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16