A is twice as good a workman as B. A takes 6 days to comlete a task. What time does B take to complete the work (in days)?
3
6
9
12
The correct Answer is:D
B can do the work in 12 days.
Related Playlists
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 130videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
A is twice as good workman as B.A takes 6 days the complete a work. In what time can B complete the work?
View SolutionA is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
View SolutionA is thrice as good a workman as B. If B takes 45 days to finish a task, then how many days will A take to finish the same task?
View SolutionL is twice as good a work man as U. If U takes 45 days to finish a task, then how many days will L take to finish the task ?
View SolutionC is 5 times as productive as B. A takes 60 days to complete a task. If A, B and C work together they can complete the task in 12 days. In how many days can B complete the task if he worked alone ?
View SolutionC is 5 times as productive as B. A takes 60 days to complete a task. If A, B and C work together they can complete the task in 12 days. In how many days can B complete the task if he worked alone ?
View SolutionA is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?
View SolutionA is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?
View SolutionA is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
View SolutionA is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?
View Solution