Doubtnut Promotions Sticky

A group of persons can do a work in 10 days. If 5 persons remains absent from first day, then the work is completed in 12 days by remaining persons. Tell how many persons were in the group initially?

A

1. 20

B

2. 25

C

3. 45

D

4. 30

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step-by-step, we will use the relationship between the number of workers, the number of days they work, and the total work done.

Step 1: Define Variables
Let the initial number of persons in the group be X.

Step 2: Calculate Total Work
The total work can be expressed in terms of the number of persons and the number of days. If X persons can complete the work in 10 days, then the total work W can be calculated as:
W=X×10

Step 3: Work Done with Absentees
If 5 persons are absent, then the number of persons working becomes X5. According to the problem, the remaining persons complete the work in 12 days. Therefore, the total work can also be expressed as:
W=(X5)×12

Step 4: Set the Equations Equal
Since both expressions represent the same total work W, we can set them equal to each other:
X×10=(X5)×12

Step 5: Expand and Rearrange the Equation
Expanding the right side gives:
10X=12X60
Now, rearranging the equation to isolate X:
10X12X=60
2X=60
2X=60

Step 6: Solve for X
Dividing both sides by 2 gives:
X=30

Conclusion
Thus, the initial number of persons in the group is 30.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Some person can do nay work in 60 days. If 8 person were more, than the work has been finished 10 days before. How many persons were there in starting ?

    A40
    B50
    C25
    D30
  • Question 2 - Select One

    If 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.

    A1
    B2
    C3
    D4
  • Question 3 - Select One

    a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?

    A17
    B24
    C30
    D22