A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
8
6
5
12
The correct Answer is:5
Step by step video, text & image solution for A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
A builder decided to build a farmhouse in 45 days. He employed 150 men in the beginning and120 more after 30 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. 5 b. 6 c. 7 d. 8
View Solution
Knowledge Check
- Question 1 - Select One
A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?
A5 daysB6 daysC8 daysD10 days - Question 2 - Select One
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
A5B6C3D9 - Question 3 - Select One
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
A1. 4 daysB2. 5 daysC3. 8 daysD4. 7 days
If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionA contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b. 114 c. 134 d. 112
View Solution