Doubtnut Promotions Sticky

A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

A

15 1 2

B

18

C

13 1 5

D

11

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will follow these steps:

Step 1: Determine the work done by A, B, and C
A can complete the work in 24 days, B in 15 days, and C in 12 days. We can find their work efficiencies (units of work done per day) by calculating:

- Work done by A in one day = 124 of the work
- Work done by B in one day = 115 of the work
- Work done by C in one day = 112 of the work

Step 2: Find the LCM of the days taken
To make calculations easier, we can find the LCM of 24, 15, and 12.

- LCM(24, 15, 12) = 120

Step 3: Convert the work into units
Assuming the total work is 120 units, we can find the efficiency of each worker:

- A's efficiency = 12024=5 units/day
- B's efficiency = 12015=8 units/day
- C's efficiency = 12012=10 units/day

Step 4: Calculate the combined efficiency of B and C
Now, we can find the combined efficiency of B and C:

- Combined efficiency of B and C = 8+10=18 units/day

Step 5: Calculate the work done by B and C in 3 days
In 3 days, B and C will complete:

- Work done by B and C in 3 days = 18×3=54 units

Step 6: Calculate the remaining work
Now, we can find the remaining work after B and C have worked for 3 days:

- Remaining work = Total work - Work done by B and C
- Remaining work = 12054=66 units

Step 7: Calculate the time taken by A to complete the remaining work
A's efficiency is 5 units/day, so the time taken by A to complete the remaining work is:

- Time taken by A = 665=13.2 days
- This can be expressed as 1315 days.

Final Answer
The number of days required by A alone to complete the remaining work is 1315 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :

    A9
    B712
    C1712
    D1212
  • Question 2 - Select One

    A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
    A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?

    A9
    B17(12)
    C12(12)
    D7(12)
  • Question 3 - Select One

    A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
    A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

    A1212days
    B1523days
    C10days
    D845days