A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?
18
11
To solve the problem, we will follow these steps:
Step 1: Determine the work done by A, B, and C
A can complete the work in 24 days, B in 15 days, and C in 12 days. We can find their work efficiencies (units of work done per day) by calculating:
- Work done by A in one day = 124 of the work
- Work done by B in one day = 115 of the work
- Work done by C in one day = 112 of the work
Step 2: Find the LCM of the days taken
To make calculations easier, we can find the LCM of 24, 15, and 12.
- LCM(24, 15, 12) = 120
Step 3: Convert the work into units
Assuming the total work is 120 units, we can find the efficiency of each worker:
- A's efficiency = 12024=5 units/day
- B's efficiency = 12015=8 units/day
- C's efficiency = 12012=10 units/day
Step 4: Calculate the combined efficiency of B and C
Now, we can find the combined efficiency of B and C:
- Combined efficiency of B and C = 8+10=18 units/day
Step 5: Calculate the work done by B and C in 3 days
In 3 days, B and C will complete:
- Work done by B and C in 3 days = 18×3=54 units
Step 6: Calculate the remaining work
Now, we can find the remaining work after B and C have worked for 3 days:
- Remaining work = Total work - Work done by B and C
- Remaining work = 120−54=66 units
Step 7: Calculate the time taken by A to complete the remaining work
A's efficiency is 5 units/day, so the time taken by A to complete the remaining work is:
- Time taken by A = 665=13.2 days
- This can be expressed as 1315 days.
Final Answer
The number of days required by A alone to complete the remaining work is 1315 days.
---
A can complete the work in 24 days, B in 15 days, and C in 12 days. We can find their work efficiencies (units of work done per day) by calculating:
- Work done by B in one day = 115 of the work
- Work done by C in one day = 112 of the work
To make calculations easier, we can find the LCM of 24, 15, and 12.
Assuming the total work is 120 units, we can find the efficiency of each worker:
- B's efficiency = 12015=8 units/day
- C's efficiency = 12012=10 units/day
Now, we can find the combined efficiency of B and C:
In 3 days, B and C will complete:
Now, we can find the remaining work after B and C have worked for 3 days:
- Remaining work = 120−54=66 units
A's efficiency is 5 units/day, so the time taken by A to complete the remaining work is:
- This can be expressed as 1315 days.
The number of days required by A alone to complete the remaining work is 1315 days.
Topper's Solved these Questions
Similar Questions
A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?View SolutionA, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :
A9B712C1712D1212 - Question 2 - Select One
A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?A9B17(12)C12(12)D7(12) - Question 3 - Select One
A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?A1212daysB1523daysC10daysD845days
A, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining tasks is:
A, B तथा C अकेले कार्य करते हुए किसी कार्य को क्रमशः 20, 16 तथा 30 दिनों में पूरा कर सकते हैं | यदि Aऔर B ने यह कार्य शुरू किया तथा उन्होंने 4 दिन कार्य करके छोड़ दिया , तो शेष कार्य पूरा करने में C को कितने दिन लगेंगे ?View SolutionA, B and C, alone can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed ?
A, B और C अकेले किसी कार्य को क्रमशः 9, 12 और 18 दिनों में कर सकते हैं | उन सभी ने साथ कार्य शुरू किया, लेकिन 3 दिन के बाद A ने कार्य छोड़ दिया | शेष कार्य कितने दिनों में समाप्त हुआ ?View SolutionA, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining tasks is:
A, B तथा C अकेले कार्य करते हुए किसी कार्य को क्रमशः 20, 16 तथा 30 दिनों में पूरा कर सकते हैं | यदि Aऔर B ने यह कार्य शुरू किया तथा उन्होंने 4 दिन कार्य करके छोड़ दिया , तो शेष कार्य पूरा करने में C को कितने दिन लगेंगे ?View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?View SolutionWorking together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:
View Solution