A and B can complete a certain work in 24 days and 42 days, respectively. A started the work and after x days, B joined him and the whole work was completed in 20 days. The value of x is:
A और B एक कार्य को क्रमशः 24 दिनों और 42 दिनों में पूरा कर सकते है। A ने काम शुरू किया और x दिनों के बाद, B भी उस कार्य में लग गया,और सारा कार्य 20 दिनों में पूरा हो गया। x का मान कितना है?
11
13
7
9
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work rates of A and B
A can complete the work in 24 days, so A's work rate is:
Work rate of A=124 work/day
B can complete the work in 42 days, so B's work rate is:
Work rate of B=142 work/day
Step 2: Find the Least Common Multiple (LCM)
To find a common work unit, we calculate the LCM of 24 and 42:
- The prime factorization of 24 is 23×31.
- The prime factorization of 42 is 21×31×71.
- The LCM is 23×31×71=168.
Step 3: Calculate the efficiencies
Now we can find the efficiency (work done per day) of A and B:
Efficiency of A=16824=7 units/day
Efficiency of B=16842=4 units/day
Step 4: Total work done in 20 days
The total work is 168 units. Since A worked for the entire 20 days, the work done by A is:
Work done by A=7 units/day×20 days=140 units
Step 5: Calculate the remaining work
The remaining work that B must complete is:
Remaining work=168−140=28 units
Step 6: Determine how long B worked
Since B's work rate is 4 units/day, the number of days B worked to complete the remaining 28 units is:
Days worked by B=28 units4 units/day=7 days
Step 7: Calculate the value of x
If B worked for 7 days and the total work was completed in 20 days, then A must have worked for:
20 days−7 days=13 days
Thus, the value of x (the number of days A worked alone before B joined) is:
x=13 days
Final Answer
The value of x is 13 days.
---
A can complete the work in 24 days, so A's work rate is:
Work rate of A=124 work/day
Work rate of B=142 work/day
To find a common work unit, we calculate the LCM of 24 and 42:
- The prime factorization of 24 is 23×31.
- The prime factorization of 42 is 21×31×71.
- The LCM is 23×31×71=168.
Now we can find the efficiency (work done per day) of A and B:
Efficiency of A=16824=7 units/day
Efficiency of B=16842=4 units/day
The total work is 168 units. Since A worked for the entire 20 days, the work done by A is:
Work done by A=7 units/day×20 days=140 units
The remaining work that B must complete is:
Remaining work=168−140=28 units
Since B's work rate is 4 units/day, the number of days B worked to complete the remaining 28 units is:
Days worked by B=28 units4 units/day=7 days
If B worked for 7 days and the total work was completed in 20 days, then A must have worked for:
20 days−7 days=13 days
Thus, the value of x (the number of days A worked alone before B joined) is:
x=13 days
The value of x is 13 days.
Topper's Solved these Questions
Similar Questions
25 persons can complete a work in 60 days. They started the work. 10 people left the work after x days. If the whole work was completed in 80 days, then what is the value of x ?
25 व्यक्ति किसी कार्य को 60 दिनों में पूरा कर सकते हैं | उन्होंने कार्य शुरू किया | x दिनों के बाद 10 लोगों ने कार्य छोड़ दिया | यदि पूरा कार्य 80 दिनों में पूरा हुआ, तो x का मान ज्ञात करें |
View SolutionA and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?
View SolutionA and B can complete a piece of work in 20 days and 30 days respectively. A works full time while B works half of the time. In how many days the entire work will be completed?
A तथा B किसी कार्य को क्रमशः 20 दिनों तथा 30 दिनों में पूरा कर सकते हैं | A पूरे समय कार्य करता है जबकि B आधे समय कार्य करता है | पूरा कार्य कितने दिनों में समाप्त हो जाएगा?
View SolutionA, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?
View SolutionA, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?
View SolutionA , B and C can finish a task in 42 days, 84 days and 28 days, respectively. A started the work. B joined him after 3 days. If C joined them after 5 days from the beginning, then for how many days did A work till the completion of the task?
A, B और C किसी कार्य को क्रमशः 42 दिन, 84 दिन और 28 दिन में कर सकते हैं | A ने कार्य शुरू किया तथा 8 3 दिन बाद उसमें शामिल हुआ | यदि C ने आरम्भ से 5 दिनों के बाद कार्य करना शुरू किया, तो A कार्य पूरा होने तक कितने दिनों तक कार्य करता रहा ?
View SolutionA, B and C can complete a piece of work in 4, 20 and 60 days respectively. Working together, they can complete the one third work in how many days ?
A, B और C किसी कार्य को क्रमशः 4, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे एक तिहाई कार्य कितने दिनों में समाप्त करेंगे ?
View SolutionA, B and C, alone can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed ?
A, B और C अकेले किसी कार्य को क्रमशः 9, 12 और 18 दिनों में कर सकते हैं | उन सभी ने साथ कार्य शुरू किया, लेकिन 3 दिन के बाद A ने कार्य छोड़ दिया | शेष कार्य कितने दिनों में समाप्त हुआ ?
View SolutionA, B and C can complete a piece of work in 20, 24 and 36 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 20, 24 और 36 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे इसी कार्य को कितने दिनों में पूरा करेंगे ?
View SolutionA, B and C can complete a piece of work in 4, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 4, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए वे इस कार्य को कितने दिनों में समाप्त करेंगे ?
View Solution