Doubtnut Promotions Sticky

A can complete one-third of a work in 5 days and B can do 25th of the same work in 10 days. They work together for 6 days. The remaining work is completed by C in 18 days. C alone will do the same work in:
A एक काम का एक तिहाई 5 दिनों में पूरा कर सकता है और B उसी काम के 25 भाग को 10 दिनों में पूरा कर सकता है। वे 6 दिनों तक एक साथ काम करते हैं। शेष कार्य C द्वारा 18 दिनों में पूरा किया जाता है। अकेले C इस काम को कितने दिनों में पूरा करेगा ?

A

50

B

30

C

25

D

45

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we need to determine how much work A, B, and C can complete individually and together.

Step 1: Determine the total work
Let's assume the total work is represented by 1 unit.

Step 2: Calculate A's work rate
A can complete one-third of the work in 5 days. Therefore, A's work rate can be calculated as:
Work done by A in 1 day=1/35=115 units/day

Step 3: Calculate B's work rate
B can complete two-fifths of the work in 10 days. Therefore, B's work rate can be calculated as:
Work done by B in 1 day=2/510=250=125 units/day

Step 4: Calculate the combined work rate of A and B
Now, we can find the combined work rate of A and B:
Combined work rate of A and B=115+125
To add these fractions, we need a common denominator. The least common multiple of 15 and 25 is 75.
115=575,125=375
So,
Combined work rate=575+375=875 units/day

Step 5: Calculate the work done by A and B in 6 days
In 6 days, A and B together can complete:
Work done in 6 days=6×875=4875=1625 units

Step 6: Calculate the remaining work
The remaining work after A and B have worked for 6 days is:
Remaining work=11625=251625=925 units

Step 7: Calculate C's work rate
C completes the remaining work in 18 days. Therefore, C's work rate can be calculated as:
Work done by C in 1 day=9/2518=9450=150 units/day

Step 8: Calculate how long C would take to complete the entire work alone
If C can do 150 units of work in one day, then the total time C would take to complete the entire work alone is:
Total time for C=1150=50 days

Final Answer
C alone will complete the same work in 50 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions