Doubtnut Promotions Sticky

A can complete a work in 20 days and B in 2212 days. They both work together for 6 days and the remaining work is completed by C in 26 days. In how many days the work will be completed, if all the three work together? /
किसी कार्य को A, 20 दिनों में पूरा कर सकता है और B उसे 2212 दिनों में पूरा कर सकता है | वे दोनों मिलकर 6 दिनों तक एक साथ कार्य करते हैं और शेष कार्य को C द्वारा 26 दिनों में पूरा किया गया है | तीनों एक साथ मिलकर उसी कार्य को कितने दिनों में पूरा करेंगे?

A

8

B

9

C

12

D

10

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step-by-step, we will first calculate the work done by A, B, and C, and then determine how long it will take for all three to complete the work together.

Step 1: Calculate the work done by A and B in one day.
- A can complete the work in 20 days, so A's work per day = 120 of the work.
- B can complete the work in 2212 days, which is 452 days. Thus, B's work per day = 245 of the work.

Step 2: Find the combined work done by A and B in one day.
- Combined work of A and B in one day = 120+245.
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 20 and 45 is 180.
- Converting the fractions:
- A's work: 120=9180
- B's work: 245=8180
- Therefore, combined work = 9180+8180=17180.

Step 3: Calculate the work done by A and B in 6 days.
- Work done by A and B in 6 days = 6×17180=102180.
- Simplifying 102180 gives 1730 of the work done.

Step 4: Calculate the remaining work.
- Total work = 1 (whole work).
- Remaining work = 11730=301730=1330.

Step 5: Calculate C's work rate.
- C completes the remaining work in 26 days, so C's work per day = 126.
- To find C's efficiency in terms of the total work, we need to determine how much work C does in one day:
- C's work in terms of the total work = 126.

Step 6: Calculate the efficiency of C.
- In 26 days, C completes 1330 of the work, so:
- C's efficiency = 133026=13780=160.

Step 7: Calculate the combined efficiency of A, B, and C.
- A's efficiency = 120
- B's efficiency = 245
- C's efficiency = 160
- Combined efficiency = 120+245+160.

Step 8: Find a common denominator for A, B, and C's efficiencies.
- The LCM of 20, 45, and 60 is 180.
- Converting the efficiencies:
- A's work: 120=9180
- B's work: 245=8180
- C's work: 160=3180
- Combined efficiency = 9+8+3180=20180=19.

Step 9: Calculate the total time taken if all three work together.
- Total work = 1 (whole work).
- Time taken = 1Combined efficiency=119=9 days.

Final Answer:
If all three work together, they will complete the work in 9 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?
    A एक कार्य को 4 दिन में कर सकता है और B उसे 12 दिन में कर सकता है। दोनों मिलकर उस कार्य को कितने दिन में पूरा करेंगे?

    A3 day / 3 दिन
    B4 day / 4 दिन
    C6 day / 6 दिन
    D2 day / 2 दिन