X can do a work in 3 day, Y does three times the same work in 8 days, and Z does five times the same work in 12 days. If they have to work together for 6 hours in a day, then in how much time can they complete the work?
X एक कार्य को 3 दिन में कर सकता है, Y, उसी कार्य का तीन गुना 8 दिन में करता है, और Z, उसी कार्य का पांच गुना 12 दिनों में करता है। यदि उन्हें प्रतिदिन 6 घंटे कार्य करना है, तो वे कितने समय में कार्य पूरा कर सकते हैं?
4 hours 10 minutes
4 hours
5 hours
5 hours 20 minutes
To solve the problem, we need to find out how long it will take for X, Y, and Z to complete the work together when they work for 6 hours a day. Let's break it down step by step.
Step 1: Calculate the total time taken by each person to complete one unit of work.
1. For X:
- X can complete the work in 3 days.
- Total hours worked by X = 3 days × 6 hours/day = 18 hours.
- Therefore, X's time to complete one unit of work = 18 hours.
2. For Y:
- Y can complete three times the work in 8 days.
- Time taken by Y to complete one unit of work = (8 days × 6 hours/day) / 3 = 48 hours / 3 = 16 hours.
- Therefore, Y's time to complete one unit of work = 16 hours.
3. For Z:
- Z can complete five times the work in 12 days.
- Time taken by Z to complete one unit of work = (12 days × 6 hours/day) / 5 = 72 hours / 5 = 14.4 hours.
- Therefore, Z's time to complete one unit of work = 14.4 hours.
Step 2: Calculate the efficiency of each worker.
- Efficiency of X = 1 / 18 (units of work per hour)
- Efficiency of Y = 1 / 16 (units of work per hour)
- Efficiency of Z = 1 / 14.4 (units of work per hour)
Step 3: Find the combined efficiency.
To find the combined efficiency, we need to sum up the individual efficiencies:
Combined Efficiency=118+116+114.4
To add these fractions, we need a common denominator. The least common multiple (LCM) of 18, 16, and 14.4 is 144.
- Convert each fraction:
- 118=8144
- 116=9144
- 114.4=10144 (since 14.4=725, thus 114.4=572=10144)
Now, adding these fractions:
Combined Efficiency=8+9+10144=27144
Step 4: Calculate the time to complete the work.
If we assume the total work is 1 unit, then the time taken to complete the work is given by:
Time=Total WorkCombined Efficiency=127144=14427 hours
Calculating 14427:
14427=5.3333 hours≈5 hours and 20 minutes
Conclusion:
Thus, if X, Y, and Z work together for 6 hours a day, they can complete the work in 5 hours and 20 minutes.
- X can complete the work in 3 days.
- Total hours worked by X = 3 days × 6 hours/day = 18 hours.
- Therefore, X's time to complete one unit of work = 18 hours.
- Y can complete three times the work in 8 days.
- Time taken by Y to complete one unit of work = (8 days × 6 hours/day) / 3 = 48 hours / 3 = 16 hours.
- Therefore, Y's time to complete one unit of work = 16 hours.
- Z can complete five times the work in 12 days.
- Time taken by Z to complete one unit of work = (12 days × 6 hours/day) / 5 = 72 hours / 5 = 14.4 hours.
- Therefore, Z's time to complete one unit of work = 14.4 hours.
- Efficiency of Y = 1 / 16 (units of work per hour)
- Efficiency of Z = 1 / 14.4 (units of work per hour)
- 118=8144
- 116=9144
- 114.4=10144 (since 14.4=725, thus 114.4=572=10144)
Topper's Solved these Questions
Similar Questions
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA and B can do a piece of work in 36 days, B and C can do the same work in 60 days. A and C can do the same work in 45 days. In how many days can B alone complete the same work?
A और B एक कार्य 36 दिनों में कर सकते हैं, B और C उसी कार्य को 60 दिनों में कर सकते हैं। A और C उसी कार्य को 45 दिनों में कर सकते हैं। B अकेले कितने दिनों में कार्य पूरा कर सकता है?View Solution
Knowledge Check
- Question 1 - Select One
If P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?A73daysB83daysC103daysD113days - Question 2 - Select One
A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
A8 daysB10 daysC12 daysD20 days - Question 3 - Select One
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?
A5511B5611C6511D6611
A and B working together can complete the work in 12 days. A can complete the work in 20 days. If B does work for half day each day, then in what time can the work be completed.
View SolutionP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View SolutionWorking for 9 hours a day. X can finish a task in 3 days, Y can finish three times of the same task in 8 days, and Z can finish five times of the same task in 12 days. Working together, in how many hours will they complete the task?
View SolutionX alone can do a work in 10 days. Y alone can do the same in 15 days. X, Y and Z together can do the same work in 3 days. In how many days can Z alone do the work?
View SolutionX alone can do a work in 10 days. Y alone can do the same in 15 days. X, Y and Z together can do the same work in 3 days. In how many days can Z alone do the work?
View Solution