Doubtnut Promotions Sticky

A can do 13 of work in 30 days, B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the work in:
A 30 दिनों में 13 कार्य कर सकता है, B, 24 दिनों में उसी कार्य के 25 भाग को कर सकता है। उन्होंने 20 दिनों तक साथ कार्य किया। C ने शेष कार्य 8 दिनों में पूरा किया। A, B और C के एक साथ कार्य करने से कार्य कितने दिनों में पूरा हो जाएगा.?

A

10 days

B

12 days

C

18 days

D

15 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will break it down into steps:

Step 1: Determine the total work in terms of work units.
A can do 13 of the work in 30 days. Therefore, the total work can be represented as:
Total Work=Work done by A in 30 days=3 units of work

Step 2: Calculate A's work rate.
Since A can complete 13 of the work in 30 days, A's work rate is:
A's work rate=1/3 work30 days=190 work units per day

Step 3: Calculate B's work rate.
B can do 25 of the work in 24 days. Therefore, B's work rate is:
B's work rate=2/5 work24 days=2120=160 work units per day

Step 4: Calculate the combined work rate of A and B.
The combined work rate of A and B is:
Combined work rate of A and B=A's work rate+B's work rate=190+160

To add these fractions, we need a common denominator. The least common multiple of 90 and 60 is 180. Thus:
190=2180,160=3180
So,
Combined work rate of A and B=2180+3180=5180=136 work units per day

Step 5: Calculate the work done by A and B in 20 days.
In 20 days, A and B together can complete:
Work done by A and B in 20 days=Combined work rate×20=136×20=2036=59 of the work

Step 6: Calculate the remaining work after A and B's contribution.
The remaining work after A and B worked together for 20 days is:
Remaining work=159=49 of the work

Step 7: Calculate C's work rate.
C completed the remaining work in 8 days, so C's work rate is:
C's work rate=49 work8 days=472=118 work units per day

Step 8: Calculate the combined work rate of A, B, and C.
Now, we can find the combined work rate of A, B, and C:
Combined work rate of A, B, and C=A's work rate+B's work rate+C's work rate
=190+160+118

Finding a common denominator (the least common multiple of 90, 60, and 18 is 180):
190=2180,160=3180,118=10180
So,
Combined work rate of A, B, and C=2180+3180+10180=15180=112 work units per day

Step 9: Calculate the time taken by A, B, and C to complete the work together.
If A, B, and C work together, they can complete the entire work in:
Time=Total WorkCombined work rate=1 work unit112 work units per day=12 days

Final Answer:
A, B, and C together will complete the work in 12 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

    A15 days
    B10 days
    C18 days
    D12 days
  • Question 2 - Select One

    A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • Question 3 - Select One

    A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days