A and B can do a job in 10 days and 5 days respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C take to finish 60% of the job?
A और B क्रमशः 10 दिनों और 15 दिनों में एक कार्य कर सकते हैं। उन्होंने दो दिनों तक एक साथ कार्य किया, जिसके बाद B को C से बदल दिया गया और अगले तीन दिनों में कार्य खत्म कर दिया गया। C को 60% कार्य पूरा करने में कितना समय लगेगा?

A

30 days

B

25 days

C

18 days

D

24 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the work rates of A and B
- A can complete the job in 10 days, so A's work rate is 110 of the job per day.
- B can complete the job in 5 days, so B's work rate is 15 of the job per day.

Step 2: Calculate the work done by A and B together in 2 days
- Work done by A in 2 days:
2×110=210=15
- Work done by B in 2 days:
2×15=25
- Total work done by A and B together in 2 days:
15+25=35

Step 3: Calculate the remaining work after 2 days
- Total work is considered as 1 (whole job). Therefore, the remaining work after 2 days is:
135=25

Step 4: Determine the work done by C in the next 3 days
- A continues to work for the next 3 days, so work done by A in 3 days:
3×110=310
- Total work done by A and B in the first 2 days and A in the next 3 days:
Total work done by A=15+310=210+310=510=12
- Therefore, the remaining work after A's contribution is:
25310=410310=110

Step 5: Calculate how much work C does in 3 days
- Since the remaining work of 110 is completed in 3 days, we can find C's work rate:
C completes 110 of the job in 3 days
- Therefore, C's work rate is:
Work rate of C=1/103=130 of the job per day

Step 6: Calculate how long C will take to finish 60% of the job
- To find out how long C will take to complete 60% of the job:
Time taken by C to complete 60%=60100÷130=60×301=1800 days
- Therefore, C will take 18 days to complete 60% of the job.

Final Answer
C will take 18 days to finish 60% of the job.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions