To do a certain work, the ratio of the efficiencies of A and B is 7: 5. Working together, they can complete the same work in 1712 days, A alone will complete the 60% of the same work in:
एक कार्य करने के लिए, A और B की क्षमता का अनुपात 7: 5 है। एक साथ कार्य करते हुए, वे 1712 दिनों में कार्य पूरा कर सकते हैं, अकेले A 60% कार्य को कब तक पूरा करेंगे :
16 days
18 days
21 Days
15 days
To solve the problem, we will follow these steps:
Step 1: Understand the given information
We know that the ratio of efficiencies of A and B is 7:5. This means for every 7 units of work A can do, B can do 5 units in the same time.
Step 2: Calculate the total efficiency when A and B work together
The combined efficiency of A and B is:
Efficiency of A+Efficiency of B=7+5=12 units of work per day
Step 3: Convert the working days into a fraction
The time taken by A and B together to complete the work is given as 1712 days, which can be converted into an improper fraction:
1712=352 days
Step 4: Calculate the total work done
Using the formula for work done:
Total Work=Efficiency×Time
Substituting the values we have:
Total Work=12 units/day×352 days=12×17.5=210 units
Step 5: Calculate the amount of work A needs to complete
We need to find out how long it will take A to complete 60% of the total work:
60% of Total Work=60100×210=126 units
Step 6: Calculate the time taken by A to complete 126 units of work
Since A's efficiency is 7 units of work per day, we can find the time taken by A to complete 126 units:
Time taken by A=WorkEfficiency=1267=18 days
Final Answer
A alone will complete 60% of the work in 18 days.
---
We know that the ratio of efficiencies of A and B is 7:5. This means for every 7 units of work A can do, B can do 5 units in the same time.
The combined efficiency of A and B is:
Efficiency of A+Efficiency of B=7+5=12 units of work per day
The time taken by A and B together to complete the work is given as 1712 days, which can be converted into an improper fraction:
1712=352 days
Using the formula for work done:
Total Work=Efficiency×Time
Substituting the values we have:
Total Work=12 units/day×352 days=12×17.5=210 units
We need to find out how long it will take A to complete 60% of the total work:
60% of Total Work=60100×210=126 units
Since A's efficiency is 7 units of work per day, we can find the time taken by A to complete 126 units:
Time taken by A=WorkEfficiency=1267=18 days
A alone will complete 60% of the work in 18 days.
Topper's Solved these Questions
Similar Questions
The ratio of the efficiencies of A, B and C is 4 : 5 : 3. Working together, they can complete that work in 25 days. A and C together will complete 35% of that work in:
A, B तथा C की कार्य क्षमता का अनुपात 4 : 5 : 3 है | एक साथ कार्य करते हुए वे 25 दिनों में कार्य पूरा कर लेते हैं | इस कार्य का 35% भाग A और C कितने दिनों में पूरा करेंगे ?
View SolutionThe ratio of the efficiencies of A, B and C is 2 : 5 : 3. Working together, they can complete a work in 27 days. B and C together can complete 4/9th part of that work in:
A, B और C की कार्य क्षमता का अनुपात 2 : 5 : 3 है | एक साथ कार्य करते हुए, वे किसी कार्य को 27 दिन में पूरा कर सकते हैं | B और C एक साथ उस कार्य के 4/9 भाग को कितने दिनों में पूरा करेंगे ?
View Solution
Knowledge Check
To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in 1712 days. A alone will complete 60% of the same work in:
A21 daysB16 daysC15 daysD18 daysTo do a certain work, the ratio of efficiency of A to that of B is 3:7.Working together, they can complete the work in 1012 days. They work together for 8 days. 60% of the remaining work will be completed by A alone in :
किसी कार्य को करने में, A की कार्य क्षमता तथा 8 की कार्य क्षमता का अनुपात 3: 7 है | एक साथ कार्य करते हुए, वे इस कार्य को 1012 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य का 60% हिस्सा A अकेले कितने दिनों में पूरा करेगा ?A512 daysB5 daysC612 daysD4 days
To do a certain work, the ratio of the efficiencies of A , B and C is 7 : 5 : 6. Working together, they can complete the same work in 35 days. B and C worked together for 21 days. The remaining work will be completed by A alone in :
एक निश्चित कार्य को करने के लिए,A, B और C की कार्य क्षमता का अनुपात 7 : 5: 6 है| एक साथ कार्य करते हुए, वे इसी कार्य को 35 दिनों में पूरा कर सकते हैं | B और C ने 21 दिनों तक कार्य किया | शेष कार्य पूरा करने में A को अकेले कितने दिन लगेंगे ?
View SolutionTo do a certain work, the ratio of efficiencies of A and B is 3:7, working together, they can complete a work in 14 days. B started the work and after working for 8 days, he left and A completed the remaining work. For how many days did A work?
एक निश्चित कार्य करने के लिए, A और B की क्षमता का अनुपात 3: 7 है, एक साथ काम करते हुए, वे 14 दिनों में इस काम पूरा कर सकते हैं। B ने काम शुरू किया और 8 दिनों तक काम करने के बाद, उसने छोड़ दिया और A ने शेष कार्य पूरा कर लिया। A ने कितने दिनों तक काम किया?
View SolutionThe efficiencies of A, B and C are in the ratio 2:5:3. Working together, they can complete a task in 12 days. In how many days can A alone complete 30% of that task?
A, B और C की कार्य क्षमता का अनुपात 2 : 5 : 3 है | एक साथ कार्य करते हुए, वे किसी कार्य को 12 दिनों में पूरा कर सकते हैं | A अकेले इस कार्य का 30% भाग कितने दिनों में पूरा करेगा ?
View SolutionThe efficiencies of A , B and C are in the ratio of 2 : 3 : 5. Working together, they can complete a task in 6 days. In how many days will A alone complete 20% of the task?
A, B और C की कार्य क्षमता का अनुपात 2 : 3 : 5 है | एक साथ कार्य करते हुए, वे किसी कार्य को 6 दिनों में पूरा कर सकते हैं | A 20% कार्य कितने दिनों में पूरा करेगा ?
View SolutionTo do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in:
किसी निश्चित कार्य को करने के लिए, X और Y की कार्य क्षमताओं का अनुपात 5: 4 है | एक साथ कार्य करते हुए वे इस कार्य को 10 दिनों में समाप्त कर सकते हैं | Y अकेले कार्य शुरू करता है और 5 दिनों के बाद छोड़ देता है | X अकेले शेष कार्य कितने दिनों में पूरा करेगा ?
View SolutionThe efficiencies of A , B and C are 2 : 5 : 3. Working together, they can complete a task in 9 days. In how many days will C alone can complete 40% of that task?
A, B और C की कार्य क्षमता का अनुपात 2 : 5 : 3 है | एक साथ कार्य करते हुए वे किसी कार्य को 9 दिनों में पूरा कर सकते हैं | C को अकेले इस कार्य का 40% भाग पूरा करने में कितने दिन लगेंगे ?
View Solution