Doubtnut Promotions Sticky

A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 40% of the job?
A और B क्रमशः10 दिनों और 5 दिनों में एक कार्य कर सकते हैं। उन्होंने दो दिनों तक एक साथ कार्य किया, जिसके बाद B को C से बदल दिया गया और अगले तीन दिनों में कार्य समाप्त हो गया। C को अकेले 40% कार्य पूरा करने में कितना समय लगेगा ?

A

18 Days

B

10 days

C

15 days

D

12 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by A and B
- A can complete the job in 10 days, so A's work rate (efficiency) is 110 of the job per day.
- B can complete the job in 5 days, so B's work rate (efficiency) is 15 of the job per day.

Step 2: Calculate the combined work done by A and B in 2 days
- In 2 days, the work done by A is:
Work by A=2×110=210=15
- In 2 days, the work done by B is:
Work by B=2×15=25
- Therefore, the total work done by A and B together in 2 days is:
Total Work=15+25=35

Step 3: Determine the remaining work after A and B worked together
- The total work is considered as 1 (the whole job), so the remaining work after 2 days is:
Remaining Work=135=25

Step 4: Work done by C in the next 3 days
- Let C's efficiency be x. Since C works for 3 days to complete the remaining work, we have:
3x=25
- Solving for x:
x=25÷3=215
- Thus, C's efficiency is 215 of the job per day.

Step 5: Calculate the time taken by C to finish 40% of the job
- 40% of the job is:
40%=40100=25
- The time taken by C to finish 25 of the job can be calculated using the formula:
Time=WorkEfficiency=25215=25×152=3

Final Answer
C will take 3 days to finish 40% of the job.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions