A and B do a work individually on alternate days. If A start the work, whole work is completed in 17 days. But when B start the work, work is completed in 1723 days. In how many days, A and B together can do the work?
837
815
825
834
The correct Answer is:D
To solve the problem, we need to determine how many days A and B together can complete the work. Let's break it down step by step.
Step 1: Determine the work done by A and B individually.
Let the total work be represented as 1 unit.
1. When A starts the work:
- A works on the 1st day, B on the 2nd day, A on the 3rd day, and so on.
- A completes the work in 17 days.
- In these 17 days, A works for 9 days (1st, 3rd, 5th, ..., 17th) and B works for 8 days (2nd, 4th, 6th, ..., 16th).
Let A's work per day be a and B's work per day be b.
From the information given:
9a+8b=1(Equation 1)
2. When B starts the work:
- B works on the 1st day, A on the 2nd day, B on the 3rd day, and so on.
- The work is completed in 1723 days, which is 533 days.
- In these 533 days, B works for 9 days (1st, 3rd, ..., 17th) and A works for 8 days.
Thus:
9b+8a=1(Equation 2)
Step 2: Solve the equations.
We have the two equations:
1. 9a+8b=1
2. 9b+8a=1
We can solve these equations simultaneously.
From Equation 1:
9a+8b=1(Multiply by 8)
72a+64b=8(Equation 3)
From Equation 2:
9b+8a=1(Multiply by 9)
72b+64a=9(Equation 4)
Now we can rearrange Equation 3 and Equation 4:
- From Equation 3: 72a+64b=8
- From Equation 4: 64a+72b=9
Step 3: Eliminate one variable.
Multiply Equation 3 by 9 and Equation 4 by 8:
648a+576b=72(Equation 5)
512a+576b=72(Equation 6)
Now, subtract Equation 6 from Equation 5:
(648a−512a)+(576b−576b)=72−72
136a=0⟹a=0
This indicates we made an error in the elimination process. Let's go back and solve the equations directly.
Step 4: Solve for a and b directly.
From Equation 1:
9a+8b=1⟹8b=1−9a⟹b=1−9a8
Substituting b in Equation 2:
9(1−9a8)+8a=1
9−81a8+8a=1
Multiply through by 8:
9−81a+64a=8
−17a=−1⟹a=117
Now substitute a back to find b:
b=1−9(117)8=1−9178=8178=117
Step 5: Calculate combined work.
Now we have:
- a=117
- b=117
The combined work done by A and B in one day:
a+b=117+117=217
Step 6: Calculate the total time taken by A and B together.
To find the time taken by A and B together to complete the work:
Time=1 unit of work217=172=8.5 days
Final Answer
Thus, A and B together can complete the work in 8.5 days.
- A works on the 1st day, B on the 2nd day, A on the 3rd day, and so on.
- A completes the work in 17 days.
- In these 17 days, A works for 9 days (1st, 3rd, 5th, ..., 17th) and B works for 8 days (2nd, 4th, 6th, ..., 16th).
Let A's work per day be a and B's work per day be b.
9a+8b=1(Equation 1)
- B works on the 1st day, A on the 2nd day, B on the 3rd day, and so on.
- The work is completed in 1723 days, which is 533 days.
- In these 533 days, B works for 9 days (1st, 3rd, ..., 17th) and A works for 8 days.
Thus:
9b+8a=1(Equation 2)
1. 9a+8b=1
2. 9b+8a=1
9a+8b=1(Multiply by 8)
72a+64b=8(Equation 3)
9b+8a=1(Multiply by 9)
72b+64a=9(Equation 4)
- From Equation 3: 72a+64b=8
- From Equation 4: 64a+72b=9
648a+576b=72(Equation 5)
512a+576b=72(Equation 6)
(648a−512a)+(576b−576b)=72−72
136a=0⟹a=0
9a+8b=1⟹8b=1−9a⟹b=1−9a8
9(1−9a8)+8a=1
9−81a8+8a=1
Multiply through by 8:
9−81a+64a=8
−17a=−1⟹a=117
b=1−9(117)8=1−9178=8178=117
- a=117
- b=117
a+b=117+117=217
Time=1 unit of work217=172=8.5 days
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?
A7 daysB3 daysC2 daysD4 days - Question 2 - Select One
A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
A15B16C10D12 - Question 3 - Select One
A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?
A30 daysB32 daysC24 daysD25 days
A can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionA works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View Solution