A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?
80
90
75
100
The correct Answer is:C
To solve the problem step by step, we will first determine the work rates of A and B, and then combine their efforts to find out how much work they can complete together in 9 days.
Step 1: Determine A's Work Rate
A can complete 50% of the job in 9 days. Therefore, in 9 days, A completes:
Work done by A in 9 days=50%
To find A's work rate per day, we can express this as:
Work rate of A=50%9 days=509% per day
Step 2: Determine B's Work Rate
B can complete 25% of the job in 9 days. Therefore, in 9 days, B completes:
Work done by B in 9 days=25%
To find B's work rate per day, we can express this as:
Work rate of B=25%9 days=259% per day
Step 3: Combine A's and B's Work Rates
Now, we will combine A's and B's work rates to find out how much work they can do together in one day:
Combined work rate=Work rate of A+Work rate of B
Substituting the values we found:
Combined work rate=509%+259%=50+259%=759% per day
Step 4: Calculate the Total Work Done in 9 Days
To find out how much work A and B can complete together in 9 days, we multiply their combined work rate by 9:
Total work in 9 days=Combined work rate×9
Substituting the combined work rate:
Total work in 9 days=759%×9=75%
Final Answer
Thus, A and B together can complete 75% of the job in 9 days.
---
A can complete 50% of the job in 9 days. Therefore, in 9 days, A completes:
Work done by A in 9 days=50%
To find A's work rate per day, we can express this as:
Work rate of A=50%9 days=509% per day
B can complete 25% of the job in 9 days. Therefore, in 9 days, B completes:
Work done by B in 9 days=25%
To find B's work rate per day, we can express this as:
Work rate of B=25%9 days=259% per day
Now, we will combine A's and B's work rates to find out how much work they can do together in one day:
Combined work rate=Work rate of A+Work rate of B
Substituting the values we found:
Combined work rate=509%+259%=50+259%=759% per day
To find out how much work A and B can complete together in 9 days, we multiply their combined work rate by 9:
Total work in 9 days=Combined work rate×9
Substituting the combined work rate:
Total work in 9 days=759%×9=75%
Thus, A and B together can complete 75% of the job in 9 days.
Topper's Solved these Questions
Similar Questions
A can do 75% of a job in 9 days and B can do half of the job in 8 days. If they work on it together, then in how many days can they do half of the job?
View SolutionA can complete one-third of a work in 5 days and B can complete 40% of the work in 10 days. In how many days both A and B together can complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?
A80B90C75D100 - Question 2 - Select One
A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
A12B6C8D9 - Question 3 - Select One
A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
A6B214C812D9
A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionP can do a job in 12 days and Q can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View SolutionA completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
View Solution