Doubtnut Promotions Sticky

A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?

A

80

B

90

C

75

D

100

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work rates of A and B, and then combine their efforts to find out how much work they can complete together in 9 days.

Step 1: Determine A's Work Rate
A can complete 50% of the job in 9 days. Therefore, in 9 days, A completes:
Work done by A in 9 days=50%
To find A's work rate per day, we can express this as:
Work rate of A=50%9 days=509% per day

Step 2: Determine B's Work Rate
B can complete 25% of the job in 9 days. Therefore, in 9 days, B completes:
Work done by B in 9 days=25%
To find B's work rate per day, we can express this as:
Work rate of B=25%9 days=259% per day

Step 3: Combine A's and B's Work Rates
Now, we will combine A's and B's work rates to find out how much work they can do together in one day:
Combined work rate=Work rate of A+Work rate of B
Substituting the values we found:
Combined work rate=509%+259%=50+259%=759% per day

Step 4: Calculate the Total Work Done in 9 Days
To find out how much work A and B can complete together in 9 days, we multiply their combined work rate by 9:
Total work in 9 days=Combined work rate×9
Substituting the combined work rate:
Total work in 9 days=759%×9=75%

Final Answer
Thus, A and B together can complete 75% of the job in 9 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete 50% of a job in 9 days and B can complete 25% of the job in 9 days if they worked alone. If they worked together how much of the job (in %) can they complete in 9 days?

    A80
    B90
    C75
    D100
  • Question 2 - Select One

    A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?

    A12
    B6
    C8
    D9
  • Question 3 - Select One

    A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

    A6
    B214
    C812
    D9