Doubtnut Promotions Sticky

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
(A) 50 (B) 75 (C) 100 (D) 150

A

100

B

125

C

50

D

75

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A


200×50=10000
10000 व्यक्तियों के द्वारा 14 कार्य होता है।
पूरे कार्य के लिए 40000 व्यक्तियों की आवश्यकता है। अतिरिक्त मजदूरों की संख्या = =40000200×150100
=4000030000100=10000100=100

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
    (A) 50 (B) 75 (C) 100 (D) 150

    A100
    B125
    C50
    D75
  • Question 2 - Select One

    A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :

    A45
    B40
    C35
    D30
  • Question 3 - Select One

    A contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?

    A30
    B20
    C15
    D10