Ratul and Pratul together can complete a task in 18 days. They start the task together, but Rahul had to leave 7 days before the work got over. As a result it took a total of 23 days to complete the task. How many days would it have taken Pratul to complete the work by himself?
63
51
72
54
The correct Answer is:A
Step by step video, text & image solution for Ratul and Pratul together can complete a task in 18 days. They start the task together, but Rahul had to leave 7 days before the work got over. As a result it took a total of 23 days to complete the task. How many days would it have taken Pratul to complete the work by himself? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?
View SolutionA and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
View Solution
Knowledge Check
- Question 1 - Select One
Rathin & Bratin together can complete a piece of work in 12 days. They start the work together but Rathin had to leave 7.5 days before the work got over. As a result it took a total of 15 days to complete the work. How many days would it have taken Bratin to complete the work by himself?
(a)20
(b)24
(c)30
(d)28A20B24C30D28 - Question 2 - Select One
A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
A72 daysB64 daysC100 daysD120 days - Question 3 - Select One
A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
A6B5C7D7.2
A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View SolutionA and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
View SolutionA and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
View SolutionTwo persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View Solution