A and B together can do a piece of work in 16 days. B and C together can do the same work in 32 days. C can complete the same work in 80 days. After A has worked for 4 days, B for 12 days, time taken by C to complete the remaining job is x days.
P, Q and R take (x - 28) days, (x - 18) days and (x - 8) days respectively to complete an another job. The three work in a rotation to complete the job with only 1 person working on a day. Who should start the job so that the job is completed in the least possible time?
P
Q
R
Any one of the three
The correct Answer is:A
To solve the problem step-by-step, we will break it down into manageable parts.
Step 1: Determine the efficiencies of A, B, and C
1. A and B together can do the work in 16 days.
- Efficiency of A + B = Total Work / Time = 160 / 16 = 10
2. B and C together can do the work in 32 days.
- Efficiency of B + C = Total Work / Time = 160 / 32 = 5
3. C can complete the work in 80 days.
- Efficiency of C = Total Work / Time = 160 / 80 = 2
Now we have:
- Efficiency of A + B = 10
- Efficiency of B + C = 5
- Efficiency of C = 2
Step 2: Find the efficiency of A and B separately
Using the equations:
- From A + B = 10 and C = 2, we can find B:
- B + C = 5
- B + 2 = 5 → B = 3
Now substituting B into A + B:
- A + 3 = 10 → A = 7
So, we have:
- Efficiency of A = 7
- Efficiency of B = 3
- Efficiency of C = 2
Step 3: Calculate the work done by A, B, and C
1. A works for 4 days:
- Work done by A = Efficiency of A × Days worked = 7 × 4 = 28
2. B works for 12 days:
- Work done by B = Efficiency of B × Days worked = 3 × 12 = 36
3. Total work done by A and B:
- Total work done = 28 + 36 = 64
4. Remaining work:
- Remaining work = Total Work - Work done = 160 - 64 = 96
Step 4: Calculate time taken by C to complete the remaining work
1. C's efficiency is 2:
- Time taken by C = Remaining Work / Efficiency of C = 96 / 2 = 48 days
Thus, x=48.
Step 5: Determine the time taken by P, Q, and R
1. P takes (x - 28) days:
- P = 48 - 28 = 20 days
2. Q takes (x - 18) days:
- Q = 48 - 18 = 30 days
3. R takes (x - 8) days:
- R = 48 - 8 = 40 days
Step 6: Calculate efficiencies of P, Q, and R
1. Efficiency of P:
- Efficiency of P = Total Work / Time = 160 / 20 = 8
2. Efficiency of Q:
- Efficiency of Q = Total Work / Time = 160 / 30 = 5.33
3. Efficiency of R:
- Efficiency of R = Total Work / Time = 160 / 40 = 4
Step 7: Determine the optimal starting person
1. Total work done in one cycle (3 days):
- Work done in 3 days = Efficiency of P + Efficiency of Q + Efficiency of R = 8 + 5.33 + 4 = 17.33
2. Total cycles needed:
- Total work = 160
- Cycles = Total work / Work done in 3 days = 160 / 17.33 ≈ 9.23 cycles
3. Remaining work after 9 cycles:
- Work done in 9 cycles = 9 × 17.33 = 156
- Remaining work = 160 - 156 = 4
4. Determine who should do the remaining work:
- If P starts, he can do 8 work in a day.
- If Q starts, he can do 5.33 work in a day.
- If R starts, he can do 4 work in a day.
Since P has the highest efficiency, he should start the job to complete it in the least possible time.
Final Answer:
P should start the job.
---
- Efficiency of A + B = Total Work / Time = 160 / 16 = 10
- Efficiency of B + C = Total Work / Time = 160 / 32 = 5
- Efficiency of C = Total Work / Time = 160 / 80 = 2
- Efficiency of A + B = 10
- Efficiency of B + C = 5
- Efficiency of C = 2
- From A + B = 10 and C = 2, we can find B:
- B + C = 5
- B + 2 = 5 → B = 3
- A + 3 = 10 → A = 7
- Efficiency of A = 7
- Efficiency of B = 3
- Efficiency of C = 2
- Work done by A = Efficiency of A × Days worked = 7 × 4 = 28
- Work done by B = Efficiency of B × Days worked = 3 × 12 = 36
- Total work done = 28 + 36 = 64
- Remaining work = Total Work - Work done = 160 - 64 = 96
- Time taken by C = Remaining Work / Efficiency of C = 96 / 2 = 48 days
- P = 48 - 28 = 20 days
- Q = 48 - 18 = 30 days
- R = 48 - 8 = 40 days
- Efficiency of P = Total Work / Time = 160 / 20 = 8
- Efficiency of Q = Total Work / Time = 160 / 30 = 5.33
- Efficiency of R = Total Work / Time = 160 / 40 = 4
- Work done in 3 days = Efficiency of P + Efficiency of Q + Efficiency of R = 8 + 5.33 + 4 = 17.33
- Total work = 160
- Cycles = Total work / Work done in 3 days = 160 / 17.33 ≈ 9.23 cycles
- Work done in 9 cycles = 9 × 17.33 = 156
- Remaining work = 160 - 156 = 4
- If P starts, he can do 8 work in a day.
- If Q starts, he can do 5.33 work in a day.
- If R starts, he can do 4 work in a day.
P should start the job.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
A12 daysB315 daysC16 daysD9313 days - Question 2 - Select One
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
A8B10C12D16 - Question 3 - Select One
A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
A4 daysB9 daysC8 daysD5 days
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View SolutionA and B together can complete a piece of work in 16 days while B and C together can complete the same work in 12 days and A and C together in 24 days. Find out the number of days that A will take to compete the work, working alone.
View SolutionA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
View SolutionA and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
View Solution