Doubtnut Promotions Sticky

A and B together can do a piece of work in 16 days. B and C together can do the same work in 32 days. C can complete the same work in 80 days. After A has worked for 4 days, B for 12 days, time taken by C to complete the remaining job is x days.
P, Q and R take (x - 28) days, (x - 18) days and (x - 8) days respectively to complete an another job. The three work in a rotation to complete the job with only 1 person working on a day. Who should start the job so that the job is completed in the least possible time?

A

P

B

Q

C

R

D

Any one of the three

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step-by-step, we will break it down into manageable parts.

Step 1: Determine the efficiencies of A, B, and C

1. A and B together can do the work in 16 days.
- Efficiency of A + B = Total Work / Time = 160 / 16 = 10

2. B and C together can do the work in 32 days.
- Efficiency of B + C = Total Work / Time = 160 / 32 = 5

3. C can complete the work in 80 days.
- Efficiency of C = Total Work / Time = 160 / 80 = 2

Now we have:
- Efficiency of A + B = 10
- Efficiency of B + C = 5
- Efficiency of C = 2

Step 2: Find the efficiency of A and B separately

Using the equations:
- From A + B = 10 and C = 2, we can find B:
- B + C = 5
- B + 2 = 5 → B = 3

Now substituting B into A + B:
- A + 3 = 10 → A = 7

So, we have:
- Efficiency of A = 7
- Efficiency of B = 3
- Efficiency of C = 2

Step 3: Calculate the work done by A, B, and C

1. A works for 4 days:
- Work done by A = Efficiency of A × Days worked = 7 × 4 = 28

2. B works for 12 days:
- Work done by B = Efficiency of B × Days worked = 3 × 12 = 36

3. Total work done by A and B:
- Total work done = 28 + 36 = 64

4. Remaining work:
- Remaining work = Total Work - Work done = 160 - 64 = 96

Step 4: Calculate time taken by C to complete the remaining work

1. C's efficiency is 2:
- Time taken by C = Remaining Work / Efficiency of C = 96 / 2 = 48 days

Thus, x=48.

Step 5: Determine the time taken by P, Q, and R

1. P takes (x - 28) days:
- P = 48 - 28 = 20 days

2. Q takes (x - 18) days:
- Q = 48 - 18 = 30 days

3. R takes (x - 8) days:
- R = 48 - 8 = 40 days

Step 6: Calculate efficiencies of P, Q, and R

1. Efficiency of P:
- Efficiency of P = Total Work / Time = 160 / 20 = 8

2. Efficiency of Q:
- Efficiency of Q = Total Work / Time = 160 / 30 = 5.33

3. Efficiency of R:
- Efficiency of R = Total Work / Time = 160 / 40 = 4

Step 7: Determine the optimal starting person

1. Total work done in one cycle (3 days):
- Work done in 3 days = Efficiency of P + Efficiency of Q + Efficiency of R = 8 + 5.33 + 4 = 17.33

2. Total cycles needed:
- Total work = 160
- Cycles = Total work / Work done in 3 days = 160 / 17.33 ≈ 9.23 cycles

3. Remaining work after 9 cycles:
- Work done in 9 cycles = 9 × 17.33 = 156
- Remaining work = 160 - 156 = 4

4. Determine who should do the remaining work:
- If P starts, he can do 8 work in a day.
- If Q starts, he can do 5.33 work in a day.
- If R starts, he can do 4 work in a day.

Since P has the highest efficiency, he should start the job to complete it in the least possible time.

Final Answer:
P should start the job.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:

    A12 days
    B315 days
    C16 days
    D9313 days
  • Question 2 - Select One

    A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?

    A8
    B10
    C12
    D16
  • Question 3 - Select One

    A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days