Doubtnut Promotions Sticky

A and B together can do a piece of work in 16 days. B and C together can do the same work in 32 days. C can complete the same work in 80 days. After A has worked for 4 days, B for 12 days, time taken by C to complete the remaining job is x days.
P, Q and R take (x - 28) days, (x - 18) days and (x - 8) days respectively to complete an another job. The three work in a rotation to complete the job with only 1 person working on a day. Who should start the job so that the job is completed in the least possible time?

A

P

B

Q

C

R

D

Any one of the three

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for A and B together can do a piece of work in 16 days. B and C together can do the same work in 32 days. C can complete the same work in 80 days. After A has worked for 4 days, B for 12 days, time taken by C to complete the remaining job is x days. P, Q and R take (x - 28) days, (x - 18) days and (x - 8) days respectively to complete an another job. The three work in a rotation to complete the job with only 1 person working on a day. Who should start the job so that the job is completed in the least possible time? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:

    A12 days
    B315 days
    C16 days
    D9313 days
  • Question 2 - Select One

    A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?

    A8
    B10
    C12
    D16
  • Question 3 - Select One

    A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days