Doubtnut Promotions Sticky

A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone?
A किसी कार्य को को समाप्त कर सकता है जबकि B को स्वतंत्र रूप से इसी कार्य को करने में 45% अधिक दिन लगते हैं। उन्होंने एक साथ 58 दिनों तक कार्य किया तथा शेष कार्य B ने अकेले 29 दिनों में पूरा किया। A इस कार्य को अकेले कितने दिनों में समाप्त कर सकता था?

A

116 days

B

118 days

C

98 days

D

120 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone? A किसी कार्य को को समाप्त कर सकता है जबकि B को स्वतंत्र रूप से इसी कार्य को करने में 45% अधिक दिन लगते हैं। उन्होंने एक साथ 58 दिनों तक कार्य किया तथा शेष कार्य B ने अकेले 29 दिनों में पूरा किया। A इस कार्य को अकेले कितने दिनों में समाप्त कर सकता था? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…

    A48 days
    B50 days
    C54 days
    D60 days
  • Question 2 - Select One

    If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?

    A60 days
    B45 days
    C40 days
    D30 days
  • Question 3 - Select One

    A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62