B is 20% more efficient than A. B started the work & do it for
x days. And then B is replaced by A, A completed the
remaining work in days. Ratio of work done by A & B is
3:2 IN how many days A & B working together complete
the whole work?
The correct Answer is:(c)
Efficiency ratio A and
And time ratio A and
i.e. in 1 day A and B together do 6 + 5 = 11 units work
Now,
B does units work
A does units work
So, total work i.e. units will be completed
by A and B together inn days
Topper's Solved these Questions
Similar Questions
B is 20% efficient than A. B started the work & do it for x days. And then B is replaced by A. And A completed the remaining work in x+8 days. Ratio of work done by A & B is 3:2. In how many day A & B working together to complete the whole work?
View SolutionA is 40 % more efficient than B. If B can complete this work in 24 days. In how many days will both A and B complete this work ?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
A10.5B8C8.4D9 - Question 2 - Select One
A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
A10.5B8C283D9 - Question 3 - Select One
A can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?
A214B257C245D203
A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View SolutionA can do 34th part of a work in 10 days and B completed the remaining part of work in 5 days. In how many days A and B working together will finish that work?
View SolutionA can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.
View SolutionA is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
View SolutionA is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View Solution