Doubtnut Promotions Sticky

Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.

A

6623

B

3313

C

1623

D

1427

Video Solution
Text Solution
Verified by Experts

The correct Answer is:(b)


Let the C do in one day = 4y work
Let the D do in one day = 5y work
2 day work of C+D=9y
In 44 days they will complete 9y×22=198y
In another 1/2 days 2y work will be done
C will take 200y4y days=50days
D will take =40 days
C and D will complete work together in
=50×4090=2009
According to condition
2009x+2009×2x=1
400+20018x=
x=3313

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days
  • Question 2 - Select One

    A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • Question 3 - Select One

    A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?

    A15
    B16
    C10
    D12