Doubtnut Promotions Sticky

P can complete a task in 15 days Q is 50% more efficient
then P. Both P and Q started working together on the
task and after few day Q lift task and P finished the
remaining 1/3of the given work. For how many days P and Q worled together.

A

3

B

5

C

4

D

6

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(c)


To solve the problem step by step, we will analyze the work done by P and Q and determine how many days they worked together.

Step 1: Determine the work rate of P
P can complete the task in 15 days. Therefore, the work rate of P is:
Work rate of P=115 (work per day)

Step 2: Determine the work rate of Q
Q is 50% more efficient than P. This means Q can do 1.5 times the work that P can do in a day. Thus, the work rate of Q is:
Work rate of Q=1.5×115=1.515=110 (work per day)

Step 3: Calculate the combined work rate of P and Q
When P and Q work together, their combined work rate is:
Combined work rate=Work rate of P+Work rate of Q=115+110
To add these fractions, we need a common denominator, which is 30:
Combined work rate=230+330=530=16 (work per day)

Step 4: Determine the total work done
Since P finished the remaining 13 of the work alone, it means that together they completed 113=23 of the work.

Step 5: Calculate the time taken by P and Q to complete 23 of the work
Let x be the number of days P and Q worked together. The amount of work they completed together in x days is:
Work done together=x×16
Setting this equal to 23:
x×16=23

Step 6: Solve for x
To solve for x, we can multiply both sides by 6:
x=23×6=4

Conclusion
P and Q worked together for 4 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P can do a work in 9 days and Q is 50% more efficient than P. In how many days can Q do it alone ?

    A1312
    B412
    C6
    D3
  • Question 2 - Select One

    P can complete a work in 72 days. Q is 33.33% more efficient
    than P. In how many days both complete the work if they
    work on alternate days starting with P?

    A56 days
    B60 days
    C62 days
    Dnone of these
  • Question 3 - Select One

    P can do a piece of work in 36 days. If Q is 50% more efficient than P, then in how many days can Q do the same work?

    A18
    B24
    C12
    D21