Doubtnut Promotions Sticky

A can do 20% of the work in 4 days, B can do 3313 % of the same work in 10 days. They worked together for 9 days. C completed the remaining work in 6 days. B and C together will complete 75% of the work in:
A 4 दिनों में 20% कार्य कर सकता है,B वही कार्य का 3313 % भाग 10 दिनों में कर सकता है। उन्होंने 9 दिनों तक एक साथ कार्य किया। C ने शेष कार्य 6 दिनों में पूरा कर लिया। B और C मिलकर 75% कार्य पूरा करेंगे

A

12 days

B

15 days

C

10 days

D

9 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work done by each person (A, B, and C) and then calculate how long B and C will take to complete 75% of the work together.

Step 1: Determine the total work done by A and B
1. Calculate A's work rate: A can do 20% of the work in 4 days. Therefore, to find out how many days A takes to complete the entire work:
Total work=100% (or 1)Days taken by A=100%20%×4 days=20 days
So, A can complete the work in 20 days.

2. Calculate B's work rate: B can do 3313% of the work in 10 days. Converting 3313% to a fraction:
3313%=1003%
To find out how many days B takes to complete the entire work:
Days taken by B=100%1003%×10 days=30 days
So, B can complete the work in 30 days.

Step 2: Calculate the work done by A and B together in 9 days
1. Calculate the work rates:
- Work rate of A = 120 (work/day)
- Work rate of B = 130 (work/day)

2. Combined work rate of A and B:
Combined work rate=120+130=3+260=560=112 (work/day)

3. Work done by A and B in 9 days:
Work done in 9 days=9×112=912=34 (or 75% of the work)

Step 3: Calculate the remaining work and C's work rate
1. Total work: Assume total work = 1 (100%).
2. Work remaining after A and B's contribution:
Remaining work=134=14

3. C completes the remaining work in 6 days:
C's work rate=146=124 (work/day)

Step 4: Calculate how long B and C will take to complete 75% of the work
1. Combined work rate of B and C:
- Work rate of B = 130
- Work rate of C = 124
Combined work rate of B and C=130+124
To add these fractions, find a common denominator (which is 120):
=4120+5120=9120=340 (work/day)

2. Calculate time taken to complete 75% of the work:
Work to be done=75%=34Time=WorkRate=34340=34×403=10 days

Final Answer:
B and C together will complete 75% of the work in 10 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • Question 2 - Select One

    A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :

    A212 days
    B3 days
    C112 days
    D2 days
  • Question 3 - Select One

    A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days