A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?
A and B
A and C
B and C
A and D
The correct Answer is:D
To solve the problem step by step, we will first determine the time taken by each individual (A, B, C, and D) to complete the work, then calculate their efficiencies, and finally analyze the pairs to find which one is the first pair.
Step 1: Determine the time taken by each worker
- A can complete the work in 4 days.
- B takes double the time of A:
Time taken by B=2×4=8 days
- C takes double the time of B:
Time taken by C=2×8=16 days
- D takes double the time of C:
Time taken by D=2×16=32 days
Step 2: Calculate the work done by each worker in one day
- A's work rate (efficiency) = 14 (since A completes the work in 4 days)
- B's work rate = 18
- C's work rate = 116
- D's work rate = 132
Step 3: Calculate the combined efficiency of each pair
1. Pair A and B:
Efficiency of A and B=14+18=28+18=38
Time taken by A and B to complete the work:
Time=138=83 days
2. Pair C and D:
Efficiency of C and D=116+132=232+132=332
Time taken by C and D to complete the work:
Time=1332=323 days
3. Pair B and C:
Efficiency of B and C=18+116=216+116=316
Time taken by B and C to complete the work:
Time=1316=163 days
4. Pair A and D:
Efficiency of A and D=14+132=832+132=932
Time taken by A and D to complete the work:
Time=1932=329 days
Step 4: Compare the pairs based on the time taken
According to the problem, one pair takes two-thirds the time needed by the second pair. We will check each pair against the others:
- Comparing A and B with C and D:
8/332/3=832=14(not two-thirds)
- Comparing B and C with A and D:
16/332/9=16×932×3=14496=32(not two-thirds)
- Comparing A and D with C and D:
32/932/3=32×332×9=39=13(not two-thirds)
- Comparing A and B with B and C:
8/316/3=816=12(not two-thirds)
Conclusion
After checking all pairs, we find that the first pair that satisfies the condition of taking two-thirds the time of the second pair is A and B.
Final Answer
The first pair is A and B.
- A can complete the work in 4 days.
- B takes double the time of A:
Time taken by B=2×4=8 days
- C takes double the time of B:
Time taken by C=2×8=16 days
- D takes double the time of C:
Time taken by D=2×16=32 days
- A's work rate (efficiency) = 14 (since A completes the work in 4 days)
- B's work rate = 18
- C's work rate = 116
- D's work rate = 132
1. Pair A and B:
Efficiency of A and B=14+18=28+18=38
Time taken by A and B to complete the work:
Time=138=83 days
Efficiency of C and D=116+132=232+132=332
Time taken by C and D to complete the work:
Time=1332=323 days
Efficiency of B and C=18+116=216+116=316
Time taken by B and C to complete the work:
Time=1316=163 days
Efficiency of A and D=14+132=832+132=932
Time taken by A and D to complete the work:
Time=1932=329 days
According to the problem, one pair takes two-thirds the time needed by the second pair. We will check each pair against the others:
8/332/3=832=14(not two-thirds)
16/332/9=16×932×3=14496=32(not two-thirds)
32/932/3=32×332×9=39=13(not two-thirds)
8/316/3=816=12(not two-thirds)
After checking all pairs, we find that the first pair that satisfies the condition of taking two-thirds the time of the second pair is A and B.
The first pair is A and B.
Topper's Solved these Questions
Similar Questions
A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
View SolutionA can do a piece of work in 6 days. B takes 8 days and Ctakes as long as A and B would take working together. B and C working together will complete the work in
View Solution
Knowledge Check
- Question 1 - Select One
P car complete a piece of wark in 3 days. Q takes triple the time taken by P,R takes 4 times that taken by Q and s takes double the time taken by R to complete the same task. They are grouped in two pairs. One of the pairs takes 212 times the taken by the other pair to complete the work. which is the second pair?
AP,SBR,RCQ,RDQ,S - Question 2 - Select One
A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
A18 daysB24 daysC16 daysD20 days - Question 3 - Select One
A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?
A16B19C25D27
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View SolutionA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
View SolutionA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?View Solution