If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then find the number of chairs made by 18 carpenters in 360 days each working 8 hours a day?
1. 1320
2. 1380
3. 1260
4. 920
The correct Answer is:B
To solve the problem, we will use the relationship between the number of workers, the number of days they work, the number of hours they work each day, and the total work done (in this case, the number of chairs made). We can use the formula:
m1⋅d1⋅h1w1=m2⋅d2⋅h2w2
Where:
- m1 = number of carpenters in the first scenario (12)
- d1 = number of days in the first scenario (240)
- h1 = hours worked per day in the first scenario (6)
- w1 = work done in the first scenario (460 chairs)
- m2 = number of carpenters in the second scenario (18)
- d2 = number of days in the second scenario (360)
- h2 = hours worked per day in the second scenario (8)
- w2 = work done in the second scenario (unknown)
1. Identify the known values:
- m1=12
- d1=240
- h1=6
- w1=460
- m2=18
- d2=360
- h2=8
2. Set up the equation using the formula:
12⋅240⋅6460=18⋅360⋅8w2
3. Calculate the left side of the equation:
Left Side=12⋅240⋅6460
- Calculate 12⋅240=2880
- Then, 2880⋅6=17280
- Finally, 17280460=37.478 (approximately)
4. Calculate the right side of the equation:
Right Side=18⋅360⋅8w2
- Calculate 18⋅360=6480
- Then, 6480⋅8=51840
5. Set the two sides equal to each other:
37.478=51840w2
6. Solve for w2:
- Cross-multiply to get:
37.478⋅w2=51840
- Now, divide both sides by 37.478:
w2=5184037.478≈1380
Final Answer:
The number of chairs made by 18 carpenters in 360 days, each working 8 hours a day, is approximately 1380 chairs.
- m1 = number of carpenters in the first scenario (12)
- d1 = number of days in the first scenario (240)
- h1 = hours worked per day in the first scenario (6)
- w1 = work done in the first scenario (460 chairs)
- m2 = number of carpenters in the second scenario (18)
- d2 = number of days in the second scenario (360)
- h2 = hours worked per day in the second scenario (8)
- w2 = work done in the second scenario (unknown)
- m1=12
- d1=240
- h1=6
- w1=460
- m2=18
- d2=360
- h2=8
12⋅240⋅6460=18⋅360⋅8w2
Left Side=12⋅240⋅6460
- Calculate 12⋅240=2880
- Then, 2880⋅6=17280
- Finally, 17280460=37.478 (approximately)
Right Side=18⋅360⋅8w2
- Calculate 18⋅360=6480
- Then, 6480⋅8=51840
37.478=51840w2
- Cross-multiply to get:
37.478⋅w2=51840
- Now, divide both sides by 37.478:
w2=5184037.478≈1380
The number of chairs made by 18 carpenters in 360 days, each working 8 hours a day, is approximately 1380 chairs.
Topper's Solved these Questions
Similar Questions
If 12 carpenters, working 6 hours a day, can make 460 chairs in 24 days, how many chairs will 18 carpenters make in 36 days, each working 8 hours a day? 1260 b. 920 c. 1320 d. 1380
View SolutionIf 2 persons working 2 hours a day for each of 2 days produce 2 articles, then the number ofarticles produced by 4 persons working 4 hours a day for each of 4 days is
View Solution
Knowledge Check
- Question 1 - Select One
If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then find the number of chairs made by 18 carpenters in 360 days each working 8 hours a day?
A92B132C138D126 - Question 2 - Select One
If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?
A15 daysB16 daysC18 daysD20 days - Question 3 - Select One
If 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?A9B18C16D12
If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution12 men and 18 boys working 712 hours a day can do a work in 60 days. If one man works equal to 2 boys, then the number of boys required to help 21 men to do twice the work in 50 days working 9 hours a day will be:
View Solution18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day
View Solution