Doubtnut Promotions Sticky

If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then find the number of chairs made by 18 carpenters in 360 days each working 8 hours a day?

A

1. 1320

B

2. 1380

C

3. 1260

D

4. 920

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we will use the relationship between the number of workers, the number of days they work, the number of hours they work each day, and the total work done (in this case, the number of chairs made). We can use the formula:

m1d1h1w1=m2d2h2w2

Where:
- m1 = number of carpenters in the first scenario (12)
- d1 = number of days in the first scenario (240)
- h1 = hours worked per day in the first scenario (6)
- w1 = work done in the first scenario (460 chairs)
- m2 = number of carpenters in the second scenario (18)
- d2 = number of days in the second scenario (360)
- h2 = hours worked per day in the second scenario (8)
- w2 = work done in the second scenario (unknown)

1. Identify the known values:
- m1=12
- d1=240
- h1=6
- w1=460
- m2=18
- d2=360
- h2=8

2. Set up the equation using the formula:
122406460=183608w2

3. Calculate the left side of the equation:
Left Side=122406460
- Calculate 12240=2880
- Then, 28806=17280
- Finally, 17280460=37.478 (approximately)

4. Calculate the right side of the equation:
Right Side=183608w2
- Calculate 18360=6480
- Then, 64808=51840

5. Set the two sides equal to each other:
37.478=51840w2

6. Solve for w2:
- Cross-multiply to get:
37.478w2=51840
- Now, divide both sides by 37.478:
w2=5184037.4781380

Final Answer:
The number of chairs made by 18 carpenters in 360 days, each working 8 hours a day, is approximately 1380 chairs.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then find the number of chairs made by 18 carpenters in 360 days each working 8 hours a day?

    A92
    B132
    C138
    D126
  • Question 2 - Select One

    If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?

    A15 days
    B16 days
    C18 days
    D20 days
  • Question 3 - Select One

    If 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
    यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?

    A9
    B18
    C16
    D12