The expenditure on gas is ₹ 450. If 6 burners light for 8 days for 6 hours per day. How many burners are required to expense ₹625, 5 hours lighting per day for 10 days?
5 burners
8 burners
9 burners
10 burners
The correct Answer is:C
To solve the problem step by step, we will use the relationship between the number of burners, time, days, and expenditure.
Step 1: Understand the given information
We know that:
- Expenditure for 6 burners for 8 days at 6 hours per day is ₹450.
- We need to find how many burners (let's call it X) are required for an expenditure of ₹625, lighting for 5 hours a day for 10 days.
Step 2: Set up the relationship
We can use the formula based on the relationship of work done:
M1×T1×D1W1=M2×T2×D2W2
Where:
- M1=6 (initial number of burners)
- T1=6 (initial hours per day)
- D1=8 (initial days)
- W1=450 (initial expenditure)
- M2=X (unknown number of burners)
- T2=5 (new hours per day)
- D2=10 (new days)
- W2=625 (new expenditure)
Step 3: Substitute the values into the formula
Substituting the known values into the formula gives us:
6×6×8450=X×5×10625
Step 4: Simplify the left side
Calculating the left side:
6×6×8450=288450=3250=1625
Step 5: Simplify the right side
Now, simplifying the right side:
X×5×10625=50X625=X12.5
Step 6: Set the two sides equal
Now we set the two sides equal to each other:
1625=X12.5
Step 7: Cross-multiply to solve for X
Cross-multiplying gives us:
16×12.5=25X
Calculating 16×12.5:
200=25X
Step 8: Solve for X
Now, divide both sides by 25:
X=20025=8
Conclusion
Thus, the number of burners required is 8.
---
We know that:
- Expenditure for 6 burners for 8 days at 6 hours per day is ₹450.
- We need to find how many burners (let's call it X) are required for an expenditure of ₹625, lighting for 5 hours a day for 10 days.
We can use the formula based on the relationship of work done:
M1×T1×D1W1=M2×T2×D2W2
Where:
- M1=6 (initial number of burners)
- T1=6 (initial hours per day)
- D1=8 (initial days)
- W1=450 (initial expenditure)
- M2=X (unknown number of burners)
- T2=5 (new hours per day)
- D2=10 (new days)
- W2=625 (new expenditure)
Substituting the known values into the formula gives us:
6×6×8450=X×5×10625
Calculating the left side:
6×6×8450=288450=3250=1625
Now, simplifying the right side:
X×5×10625=50X625=X12.5
Now we set the two sides equal to each other:
1625=X12.5
Cross-multiplying gives us:
16×12.5=25X
Calculating 16×12.5:
200=25X
Now, divide both sides by 25:
X=20025=8
Thus, the number of burners required is 8.
Topper's Solved these Questions
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
- Question 1 - Select One
If the expenditure of gas on burning 6 burners for 6 hours a day for 8 days is 450, then how many burners can be used for 10 days at 5 hours a day for Rs 625
A12B16C4D8 - Question 2 - Select One
If 10 men finish 10 unit work in 10 days at 10 hours per day, then how many units of work will 5 men complete in 5 days at 5 hours per day ?
A1.25 unitsB1.2C2.5DNone of these - Question 3 - Select One
18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
A25B15C20D9
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View SolutionA earns Rs 180 per hour and works for 7 hours per day. B earns Rs. 160 per hour and works for 5 hours per day. what is the ratio of per day wages of A and B? /
A 180 रुपये प्रति घंटे कमाता है तथा एक दिन में 7 घंटे कार्य करता है | B 160 रुपये प्रति घंटे कमाता है और प्रतिदिन 5 घंटे कार्य करता है | A और B के दैनिक वेतन का अनुपात क्या है ?View SolutionIf 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?
View Solution