It takes six technicians a total of 10 hr to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11 am, and one tech nician per hour is added beginning at 5 pm, at what time will the server be completed?
6.40 pm
7pm
7.20 pm
8pm
The correct Answer is:D
Step by step video, text & image solution for It takes six technicians a total of 10 hr to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11 am, and one tech nician per hour is added beginning at 5 pm, at what time will the server be completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished? a. 11:30 a.m. b. 12 noon c. 12:30 p.m. d. 1 p.m.
View SolutionA walks around a circular field at the rate of one round per hour while B runs around it at the rate of six rounds per hour. They start in the same direction from the same point at 7.30 a.m. They shall first cross each other at:
View Solution
Knowledge Check
- Question 1 - Select One
Two men start walking from same point at same time in same direction to take a round of circular route. If one take 10 min and second take 15 min complete the round, at what time will they meet each other ?
A30 minB33 minC40 minD45 min - Question 2 - Select One
Machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print the same number of books in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished ?
A11:30 AMB12 noonC12 :30 p.m.D1 p.m. - Question 3 - Select One
Study the following information Carefully and answer the given questions : Given an input, a machine generates pass codes for the six batches each day as follows :
Input : these icons were taken out from the sea
Pass codes :
Batch I : from sea the out taken were incons these
Batch II : from icons these were taken out the sea
Batch III : from icons out sea the taken were these
Batch IV : from icons out sea these were taken the
and so on.
First batch starts at 10.00 a.m. and each batch is for one hour. There is a rest period of one hour after the end of the fourth batch.
What will be the pass code for the batch at 3.00 p.m. if input is 'four of the following five form a group' ?Aa five following form four group the ofBa five following form group the of fourCa five following form four of the groupDa five following form four group of the
"SANJAY Book Depot" can print one lakhs books in 8 hours. "DEVINDER & Sons" can print the same number of books in 10 hours while "HARISH & Sons" can print the same in 12 hours. All of them started printing at 0900 hrs. "SANJAY" is stopped at 1100 hrs and the remanining two machines complete the remaining leftover work. Approximately at what time will the printing of one lakhs books be completed?
View SolutionTwo people A and B are at a distance of 260km from each other at 9:00 a.m. A immediately starts moving towards B at a speed of 25km/h and at 11:00 a.m. B starts moving towards A at a speed of 10km/hr. At what time (in p.m) will they meet each other?
View SolutionStudy the following information Carefully and answer the given questions : Given an input, a machine generates pass codes for the six batches each day as follows :
Input : these icons were taken out from the sea
Pass codes :
Batch I : from sea the out taken were incons these
Batch II : from icons these were taken out the sea
Batch III : from icons out sea the taken were these
Batch IV : from icons out sea these were taken the
and so on.
First batch starts at 10.00 a.m. and each batch is for one hour. There is a rest period of one hour after the end of the fourth batch.
If the pass code for the batch at 1.00 p.m. on a day was
'back go here people who settle want to', what was the pass code for the batch at 3.00 p.m. on that day ?View SolutionGiven an input,a coding machine
generates pass codes for the six batches every day as follows:
Input : see the little squirrels jumping here and there
Pass codes :
Batch I : jumping see here the and little there squirrels
Batch II . the and here little see there jumping squirrels
Batch III : see the there and jumping here squlrrels little
Batch IV : and jumping there herre the squirrels see little and so on.
The first batch timing is 10.00 a.m. and each batch is of
One hour's duration. There is a rest period of one hour after
the work for the fourth batch is over .
On a particular day, Mr X was to begin the work in the
batch at 11.00 a.m. with a pass code 'he slowly recedes
to his inner apartment intellect'. However, he came late
on that day and hence joined the batch at 12 noon. What
was his pass code then ?View SolutionStudy the following information Carefully and answer the given questions : Given an input, a machine generates pass codes for the six batches each day as follows :
Input : these icons were taken out from the sea
Pass codes :
Batch I : from sea the out taken were incons these
Batch II : from icons these were taken out the sea
Batch III : from icons out sea the taken were these
Batch IV : from icons out sea these were taken the
and so on.
First batch starts at 10.00 a.m. and each batch is for one hour. There is a rest period of one hour after the end of the fourth batch.
The pass code for the first batch on a day was 'he so used to sell the surplus items'. What was the input on that day ?View Solution