6 persons earn ₹ 8,400 in a week, if they work 8 hours per day then how much amount would be earned by 9 persons in a week if they do the work 6 hours per day?
₹ 9,450
₹ 1,350
₹ 9,000
₹ 7,200
The correct Answer is:A
To solve the problem step by step, we can follow these calculations:
Step 1: Understand the given information
We know that:
- 6 persons earn ₹8,400 in a week.
- They work 8 hours per day.
We need to find out how much 9 persons would earn in a week if they work 6 hours per day.
Step 2: Calculate the total hours worked by 6 persons in a week
First, we need to calculate the total hours worked by the 6 persons in a week.
Total hours worked by 6 persons in a week = Number of persons × Hours per day × Days per week
Assuming they work 7 days a week:
- Total hours = 6 persons × 8 hours/day × 7 days = 336 hours
Step 3: Calculate the earning per hour for 6 persons
Now, we can find out how much they earn per hour.
Earning per hour = Total earning / Total hours worked
- Earning per hour = ₹8,400 / 336 hours = ₹25 per hour
Step 4: Calculate the total hours worked by 9 persons in a week
Next, we calculate the total hours worked by 9 persons who work 6 hours per day.
Total hours worked by 9 persons in a week = Number of persons × Hours per day × Days per week
- Total hours = 9 persons × 6 hours/day × 7 days = 378 hours
Step 5: Calculate the total earning for 9 persons
Now, we can calculate how much 9 persons would earn in a week.
Total earning for 9 persons = Earning per hour × Total hours worked
- Total earning = ₹25/hour × 378 hours = ₹9,450
Conclusion
Thus, the amount earned by 9 persons in a week, working 6 hours per day, is ₹9,450.
---
We know that:
- 6 persons earn ₹8,400 in a week.
- They work 8 hours per day.
First, we need to calculate the total hours worked by the 6 persons in a week.
- Total hours = 6 persons × 8 hours/day × 7 days = 336 hours
Now, we can find out how much they earn per hour.
- Earning per hour = ₹8,400 / 336 hours = ₹25 per hour
Next, we calculate the total hours worked by 9 persons who work 6 hours per day.
- Total hours = 9 persons × 6 hours/day × 7 days = 378 hours
Now, we can calculate how much 9 persons would earn in a week.
- Total earning = ₹25/hour × 378 hours = ₹9,450
Thus, the amount earned by 9 persons in a week, working 6 hours per day, is ₹9,450.
Topper's Solved these Questions
Similar Questions
If 10 men complete half work in 12 days when they work 8 hours per day, In how many days 18 men complete the full when they work 6 hours/day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
40 persons can do a work in 15 days if they work 8 hours per day, then in how many days 60 persons can complete the double work if they work 4 hours per day? If the work done by 3 persons of first type in 2 hours is same as the work done by 4 persons of the second type in 3 hours.
A25 daysB30 daysC80 daysD35 days30 persons can complete a work in 10 days. If they work 4 hours per day, then in how many days 45 persons can complete double the work if they work 8 hours per day? It is known that 2 persons of first type can do the same work in 2 hours that can be completed by 4 persons of 2nd type in 1 hour.
A623 daysB9 daysC8 daysD7 days5 persons paint a house at 8 hours per day in 3 days. In how many days will 1 man paint the house if he works 4 hours per day ?
A30B152C65D310
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionIf 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.
View Solution36 personn working 8 hours a day can do 3 units of working in 12 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
View Solution39 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons working 6 hours a day complete the work ?
View SolutionA can finish a work in 10 days if he works 4 hours per day. B can complete it in 15 days if he works 5 hours per day. If they work 10 hours per day, then in how many days the work will be finished?
View Solution