6 persons earn ₹ 8,400 in a week, if they work 8 hours per day then how much amount would be earned by 9 persons in a week if they do the work 6 hours per day?

A

₹ 9,450

B

₹ 1,350

C

₹ 9,000

D

₹ 7,200

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these calculations:

Step 1: Understand the given information
We know that:
- 6 persons earn ₹8,400 in a week.
- They work 8 hours per day.

We need to find out how much 9 persons would earn in a week if they work 6 hours per day.

Step 2: Calculate the total hours worked by 6 persons in a week
First, we need to calculate the total hours worked by the 6 persons in a week.

Total hours worked by 6 persons in a week = Number of persons × Hours per day × Days per week

Assuming they work 7 days a week:
- Total hours = 6 persons × 8 hours/day × 7 days = 336 hours

Step 3: Calculate the earning per hour for 6 persons
Now, we can find out how much they earn per hour.

Earning per hour = Total earning / Total hours worked
- Earning per hour = ₹8,400 / 336 hours = ₹25 per hour

Step 4: Calculate the total hours worked by 9 persons in a week
Next, we calculate the total hours worked by 9 persons who work 6 hours per day.

Total hours worked by 9 persons in a week = Number of persons × Hours per day × Days per week
- Total hours = 9 persons × 6 hours/day × 7 days = 378 hours

Step 5: Calculate the total earning for 9 persons
Now, we can calculate how much 9 persons would earn in a week.

Total earning for 9 persons = Earning per hour × Total hours worked
- Total earning = ₹25/hour × 378 hours = ₹9,450

Conclusion
Thus, the amount earned by 9 persons in a week, working 6 hours per day, is ₹9,450.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 40 persons can do a work in 15 days if they work 8 hours per day, then in how many days 60 persons can complete the double work if they work 4 hours per day? If the work done by 3 persons of first type in 2 hours is same as the work done by 4 persons of the second type in 3 hours.

    A25 days
    B30 days
    C80 days
    D35 days
  • 30 persons can complete a work in 10 days. If they work 4 hours per day, then in how many days 45 persons can complete double the work if they work 8 hours per day? It is known that 2 persons of first type can do the same work in 2 hours that can be completed by 4 persons of 2nd type in 1 hour.

    A623 days
    B9 days
    C8 days
    D7 days
  • 5 persons paint a house at 8 hours per day in 3 days. In how many days will 1 man paint the house if he works 4 hours per day ?

    A30
    B152
    C65
    D310