Doubtnut Promotions Sticky

16 men are able to complete a piece of work in 12 days working 14 hours a day. How long will 28 men, working 12 hours a day, take to complete the work?

A

10 days

B

7 days

C

8 days

D

6 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we will first determine the total amount of work done in terms of man-hours, and then find out how long it will take for 28 men working 12 hours a day to complete the same amount of work.

Step 1: Calculate the total work done by 16 men in 12 days working 14 hours a day.

- Number of men (m1) = 16
- Number of days (d1) = 12
- Hours worked per day (h1) = 14

Total work (W) can be calculated as:
W=m1×d1×h1
Substituting the values:
W=16×12×14

Step 2: Perform the multiplication to find the total work.

Calculating:
W=16×12=192
Then,
W=192×14=2688 man-hours

Step 3: Determine how many man-hours 28 men working 12 hours a day can provide.

- Number of men (m2) = 28
- Hours worked per day (h2) = 12

The total work done by 28 men in one day is:
Work done in one day=m2×h2=28×12

Calculating:
Work done in one day=28×12=336 man-hours

Step 4: Calculate how many days (d2) it will take for 28 men to complete the total work.

We know the total work is 2688 man-hours and the work done in one day by 28 men is 336 man-hours. We can find the number of days (d2) required by dividing the total work by the work done in one day:
d2=WWork done in one day=2688336

Step 5: Perform the division to find the number of days.

Calculating:
d2=2688336=8

Final Answer:
It will take 28 men working 12 hours a day 8 days to complete the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?

    A30 days
    B20 days
    C60 days
    D40 days
  • Question 2 - Select One

    8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?

    A2012 days
    B2035 days
    C21days
    D2047 days
  • Question 3 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611

    A5511
    B5611
    C6511
    D6611