8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed
7 days
6 days
5.25 days
3.7 days
The correct Answer is:(d)
One day work of women = half of work daon by men
in one day
Let efficiency of one women = w unit/day
Man's efficiency = 2w unit/day
Total work =(8×2w+5×w)×7
= 147 w unit
9 men and 3 women start work for 4 days
work done in 4 days =(9×2w+3×w)×4=84w
4 women replace 4 man
=(5×2w+7×w)=17w
Days required =147w−84w17w=63w17w=3.7days
Related Playlists
Similar Questions
8 men and 4 women together can complete a piece of work in
6 days. The work done by a man in one day is diuble the
work done by a woman in one day. If 8 men and 4 women
started working and after 2 days 4 men left and 4 new women
joined, in how many more days will the work be complete?View Solution8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?
View Solution8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work.
Quantity I: more days required to complete the work
II: 5 daysView Solution10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View Solution10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionThree men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View Solution2 men and 3 women can do a piece of work in 16 days . In how many days can 4 men and 6 women do the same work?
View Solution3 men or 4 women can do a piece of work in 43 days. In how many days 7 men & 5 women can do the same work ?
View Solution