Doubtnut Promotions Sticky

8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed

A

7 days

B

6 days

C

5.25 days

D

3.7 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:(d)


One day work of women = half of work daon by men
in one day
Let efficiency of one women = w unit/day
Man's efficiency = 2w unit/day
Total work =(8×2w+5×w)×7
= 147 w unit
9 men and 3 women start work for 4 days
work done in 4 days =(9×2w+3×w)×4=84w
4 women replace 4 man
=(5×2w+7×w)=17w
Days required =147w84w17w=63w17w=3.7days

|
Updated on:21/07/2023

Related Playlists


Similar Questions