A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is
556 days
614 days
312 days
334 days
The correct Answer is:C
To solve the problem, we will follow these steps:
Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 6 days, so A's work per day = 16 of the work.
- B can complete the work in 12 days, so B's work per day = 112 of the work.
- C can complete the work in 15 days, so C's work per day = 115 of the work.
Step 2: Find the combined work done by A, B, and C in one day.
- Combined work per day = A's work + B's work + C's work
- Combined work per day = 16+112+115
To add these fractions, we need a common denominator. The least common multiple (LCM) of 6, 12, and 15 is 60.
- 16=1060
- 112=560
- 115=460
Now, adding them together:
- Combined work per day = 1060+560+460=1960
Step 3: Calculate the total work done after 18 of the work is completed.
- Total work can be considered as 1 unit (or 120 units for easier calculation).
- Work completed after 18 of the work = 18 of 120 = 15 units.
Step 4: Calculate the remaining work.
- Remaining work = Total work - Work completed = 120 - 15 = 105 units.
Step 5: Calculate the work done by A and B together.
- A's work per day = 16
- B's work per day = 112
- Combined work per day by A and B = 16+112
Finding a common denominator (which is 12):
- 16=212
- 112=112
Combined work per day by A and B:
- Combined work = 212+112=312=14
Step 6: Calculate the time taken to finish the remaining work.
- Remaining work = 105 units
- Work done by A and B together in one day = 14 of the total work (which is 120 units).
To find how many days it takes to complete 105 units:
- If A and B together do 14 of 120 units in one day, they do 30 units in one day.
- Time taken to finish 105 units = 10530=3.5 days.
Final Answer:
The time taken to finish the remaining work is 3.5 days.
---
- A can complete the work in 6 days, so A's work per day = 16 of the work.
- B can complete the work in 12 days, so B's work per day = 112 of the work.
- C can complete the work in 15 days, so C's work per day = 115 of the work.
- Combined work per day = A's work + B's work + C's work
- Combined work per day = 16+112+115
- 112=560
- 115=460
- Combined work per day = 1060+560+460=1960
- Total work can be considered as 1 unit (or 120 units for easier calculation).
- Work completed after 18 of the work = 18 of 120 = 15 units.
- Remaining work = Total work - Work completed = 120 - 15 = 105 units.
- A's work per day = 16
- B's work per day = 112
- Combined work per day by A and B = 16+112
- 16=212
- 112=112
- Combined work = 212+112=312=14
- Remaining work = 105 units
- Work done by A and B together in one day = 14 of the total work (which is 120 units).
- If A and B together do 14 of 120 units in one day, they do 30 units in one day.
- Time taken to finish 105 units = 10530=3.5 days.
The time taken to finish the remaining work is 3.5 days.
Topper's Solved these Questions
Similar Questions
A,B and C can do a piece of work in 4 days, 5 days and 7 days respectively. They get ₹ 415 for completing the job. If A, B and C have worked together to complete the job, what is A's share?
View SolutionA,B and C can do a piece of work in 4 days, 5 days and 7 days respectively. They get ₹ 415 for completing the job. If A, B and C have worked together to complete the job, what is A's share?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is
A556 daysB514 daysC312 daysD334 days - Question 2 - Select One
A, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?
A2daysB3daysC5daysD4days - Question 3 - Select One
A, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?
A3B4C5D6
A, B and C can do a piece of work in 4 days , 5 days, and 7 days, respectively get Rs.415 for completing the job. If A,B and C have worked together to complete the job, what is A's share?
View SolutionA and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then, the total number of days needed for the completion of the work is
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?
View Solution