Veer is 40% less efficient than Bhavya and both complete the work together in 30 days, if Abhishek takes 10 days less as Veer and Bhavya takes together. Then find how many days will be required to complete the work, if all three work together?
16 days
12 days
10 days
8 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine the efficiencies of Veer and Bhavya.
Let Bhavya's efficiency be 100 units of work per day. Since Veer is 40% less efficient than Bhavya, we can calculate Veer's efficiency as follows:
Veer's efficiency=100−(40% of 100)=100−40=60 units of work per day.
Step 2: Calculate the combined efficiency of Veer and Bhavya.
The combined efficiency of Veer and Bhavya is:
Combined efficiency=Bhavya's efficiency+Veer's efficiency=100+60=160 units of work per day.
Step 3: Calculate the total work done.
Since Veer and Bhavya together complete the work in 30 days, we can calculate the total work as follows:
Total Work=Combined efficiency×Time=160 units/day×30 days=4800 units.
Step 4: Determine the time taken by Abhishek.
We know that Abhishek takes 10 days less than the time taken by Veer and Bhavya together. The time taken by Veer and Bhavya together is 30 days, so:
Time taken by Abhishek=30−10=20 days.
Step 5: Calculate Abhishek's efficiency.
Using the total work calculated earlier, we can find Abhishek's efficiency:
Abhishek's efficiency=Total WorkTime taken by Abhishek=4800 units20 days=240 units of work per day.
Step 6: Calculate the total efficiency of all three working together.
Now, we can find the total efficiency when all three work together:
Total efficiency=Bhavya's efficiency+Veer's efficiency+Abhishek's efficiency=100+60+240=400 units of work per day.
Step 7: Calculate the time required for all three to complete the work together.
Finally, we can find out how many days it will take for all three to complete the total work together:
Time required=Total WorkTotal efficiency=4800 units400 units/day=12 days.
Final Answer:
Thus, the time required for all three to complete the work together is 12 days.
---
Let Bhavya's efficiency be 100 units of work per day. Since Veer is 40% less efficient than Bhavya, we can calculate Veer's efficiency as follows:
The combined efficiency of Veer and Bhavya is:
Since Veer and Bhavya together complete the work in 30 days, we can calculate the total work as follows:
We know that Abhishek takes 10 days less than the time taken by Veer and Bhavya together. The time taken by Veer and Bhavya together is 30 days, so:
Using the total work calculated earlier, we can find Abhishek's efficiency:
Now, we can find the total efficiency when all three work together:
Finally, we can find out how many days it will take for all three to complete the total work together:
Thus, the time required for all three to complete the work together is 12 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
If A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View SolutionIf A & B completed a work together in 6 days . If A completed the same work in 10 days alone . Then in how many days will B complete the same work alone ?
View Solution
Knowledge Check
- Question 1 - Select One
A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) days - Question 2 - Select One
A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) days - Question 3 - Select One
A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42
Acan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
View SolutionA and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
View SolutionB works four times as much as A. If B takes 15 days less than A to complete this work. In how many days will A and B alone complete this work ?
View SolutionIf A,B and C can respectively complete a piece of work in 20,24 and 36 days respectively .how many days will they take to complete the work, if they work together?
View SolutionIf A, B and C can respectively complete a piece of work in 20, 24 and 36 days respectively, how many days will they take to complete the work, if they work together?
View Solution