Doubtnut Promotions Sticky

Each of A, B, C and D need a unique time to do a certain work. A can do the work in x days and B can do the work in 2x days. A started the work and do it for 2229days then he is replaced by B, who completed remaining work in same time as C and D together can complete the whole work. The ratio of the efficiency of C and D is 4 : 5. If C and D work for alternative days starting from C then they can do the total work in 4412days.
A and B together can compete 225% of the work in how many days?

A

6623 days

B

60 days

C

50 days

D

25 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the information given in the question and derive the necessary values.

Step 1: Determine the total work done by C and D
- The efficiency ratio of C and D is given as 4:5.
- When C and D work alternately starting from C, they complete the work in 4412 days.
- First, convert 4412 days into improper fraction:
4412=892 days
- In 2 days, C and D together complete:
4+5=9 units of work
- In 44 days, they will complete:
892÷2=44.5 days44 complete cycles of 2 days+1 day of C
- Therefore, the total work done in 44 complete cycles:
44×9=396 units
- On the last day, C works for half a day, completing:
42=2 units
- Thus, the total work done is:
396+2=398 units

Step 2: Calculate the efficiencies of A and B
- Let A's time to complete the work be x days, then B's time is 2x days.
- The efficiency of A is:
Efficiency of A=1x (work per day)
- The efficiency of B is:
Efficiency of B=12x

Step 3: Calculate the work done by A in 2229 days
- Convert 2229 into improper fraction:
2229=2009 days
- Work done by A in this time:
Work by A=2009×1x=2009x

Step 4: Calculate remaining work
- Total work is 398 units, so remaining work after A's contribution is:
Remaining Work=3982009x

Step 5: Determine the time taken by B to finish the remaining work
- Since B completes the remaining work in the same time as C and D can complete the whole work, we know:
3982009x12x=Time taken by B
- The time taken by C and D together to complete the whole work is:
39892=398×29=7969 days

Step 6: Set up the equation
- Equating the time taken by B to finish the remaining work to the time taken by C and D:
3982009x12x=7969
- Solving this equation will yield the value of x.

Step 7: Calculate the total work A and B can complete together in 225%
- Total work is 398 units, so 225% of the work is:
398×225100=448.5 units
- Combined efficiency of A and B:
Combined Efficiency=1x+12x=32x
- Time taken by A and B together to complete 448.5 units:
Time=448.532x=448.5×2x3=897x3

Step 8: Substitute x and calculate the final answer
- Substitute the value of x obtained from previous calculations to find the total time.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A66(2/3)
    B33(1/3)
    C16(2/3)
    D14(2/7)
  • Question 2 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A6623
    B3313
    C1623
    D1427
  • Question 3 - Select One

    A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days