Doubtnut Promotions Sticky

A certain work was started by 4 men and 10 women who completed 50% of the work in 6 days, if another 2 men and 2 women joined them and they could complete 2 3 rd of the remaining work in three days. How many men along with 6 women are required to complete the remaining work in two more days?

A

3

B

5

C

6

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will break down the information given and calculate the required number of men along with 6 women to complete the remaining work in two days.

Step 1: Calculate the total work done by 4 men and 10 women in 6 days.

Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.

The total work done by 4 men and 10 women in 1 day is:
Work in 1 day=4M+10W

In 6 days, the work done is:
Work in 6 days=6×(4M+10W)=24M+60W

Since this work is 50% of the total work, we can say:
24M+60W=12Total Work
Thus, the total work T is:
T=2(24M+60W)=48M+120W

Step 2: Calculate the remaining work after the first 6 days.

After completing 50% of the work, the remaining work is:
Remaining Work=TT2=T2=24M+60W

Step 3: Calculate the work done by 6 men and 12 women in 3 days.

Now, 2 more men and 2 more women join, making it 6 men and 12 women. The work done by them in 1 day is:
Work in 1 day=6M+12W

In 3 days, the work done is:
Work in 3 days=3×(6M+12W)=18M+36W

According to the problem, they complete 23 of the remaining work in these 3 days:
18M+36W=23×(24M+60W)

Step 4: Set up the equation to find the relationship between M and W.

Calculating 23 of the remaining work:
23×(24M+60W)=16M+40W

Setting the two expressions equal gives:
18M+36W=16M+40W

Rearranging:
2M=4WM=2W

Step 5: Calculate the total work in terms of W.

Substituting M=2W into the total work:
T=48(2W)+120W=96W+120W=216W

Step 6: Calculate the remaining work.

The remaining work is:
Remaining Work=24M+60W=24(2W)+60W=48W+60W=108W

Step 7: Determine the work left to be completed in 2 days.

Let X be the number of men required along with 6 women to complete the remaining work in 2 days. The total work done by X men and 6 women in 2 days is:
Work in 2 days=2(XM+6W)=2(X(2W)+6W)=4XW+12W

Setting this equal to the remaining work:
4XW+12W=108W

Step 8: Solve for X.

Dividing the entire equation by W (assuming W0):
4X+12=108
4X=10812
4X=96
X=964=24

Conclusion

Thus, the number of men required along with 6 women to complete the remaining work in 2 days is:
Number of men=24

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?

    A9 days
    B5 days
    C6 days
    D7 days
  • Question 2 - Select One

    Where 6 men and 9 women can complete a piece of work in 10 days, What is the time taken by 4 men and 6 women to complete it ?

    A10 days
    B12 days
    C15 days
    D18 days
  • Question 3 - Select One

    Three men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?

    A1 days
    B2 days
    C3 days
    D4 days