A certain work was started by 4 men and 10 women who completed 50% of the work in 6 days, if another 2 men and 2 women joined them and they could complete rd of the remaining work in three days. How many men along with 6 women are required to complete the remaining work in two more days?
3
5
6
9
The correct Answer is:C
To solve the problem step by step, we will break down the information given and calculate the required number of men along with 6 women to complete the remaining work in two days.
Step 1: Calculate the total work done by 4 men and 10 women in 6 days.
Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.
The total work done by 4 men and 10 women in 1 day is:
Work in 1 day=4M+10W
In 6 days, the work done is:
Work in 6 days=6×(4M+10W)=24M+60W
Since this work is 50% of the total work, we can say:
24M+60W=12Total Work
Thus, the total work T is:
T=2(24M+60W)=48M+120W
Step 2: Calculate the remaining work after the first 6 days.
After completing 50% of the work, the remaining work is:
Remaining Work=T−T2=T2=24M+60W
Step 3: Calculate the work done by 6 men and 12 women in 3 days.
Now, 2 more men and 2 more women join, making it 6 men and 12 women. The work done by them in 1 day is:
Work in 1 day=6M+12W
In 3 days, the work done is:
Work in 3 days=3×(6M+12W)=18M+36W
According to the problem, they complete 23 of the remaining work in these 3 days:
18M+36W=23×(24M+60W)
Step 4: Set up the equation to find the relationship between M and W.
Calculating 23 of the remaining work:
23×(24M+60W)=16M+40W
Setting the two expressions equal gives:
18M+36W=16M+40W
Rearranging:
2M=4W⟹M=2W
Step 5: Calculate the total work in terms of W.
Substituting M=2W into the total work:
T=48(2W)+120W=96W+120W=216W
Step 6: Calculate the remaining work.
The remaining work is:
Remaining Work=24M+60W=24(2W)+60W=48W+60W=108W
Step 7: Determine the work left to be completed in 2 days.
Let X be the number of men required along with 6 women to complete the remaining work in 2 days. The total work done by X men and 6 women in 2 days is:
Work in 2 days=2(XM+6W)=2(X(2W)+6W)=4XW+12W
Setting this equal to the remaining work:
4XW+12W=108W
Step 8: Solve for X.
Dividing the entire equation by W (assuming W≠0):
4X+12=108
4X=108−12
4X=96
X=964=24
Conclusion
Thus, the number of men required along with 6 women to complete the remaining work in 2 days is:
Number of men=24
Work in 1 day=4M+10W
Work in 6 days=6×(4M+10W)=24M+60W
24M+60W=12Total Work
Thus, the total work T is:
T=2(24M+60W)=48M+120W
Remaining Work=T−T2=T2=24M+60W
Work in 1 day=6M+12W
Work in 3 days=3×(6M+12W)=18M+36W
18M+36W=23×(24M+60W)
23×(24M+60W)=16M+40W
18M+36W=16M+40W
2M=4W⟹M=2W
T=48(2W)+120W=96W+120W=216W
Remaining Work=24M+60W=24(2W)+60W=48W+60W=108W
Work in 2 days=2(XM+6W)=2(X(2W)+6W)=4XW+12W
4XW+12W=108W
4X+12=108
4X=108−12
4X=96
X=964=24
Number of men=24
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
A9 daysB5 daysC6 daysD7 days - Question 2 - Select One
Where 6 men and 9 women can complete a piece of work in 10 days, What is the time taken by 4 men and 6 women to complete it ?
A10 daysB12 daysC15 daysD18 days - Question 3 - Select One
Three men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
A1 daysB2 daysC3 daysD4 days
45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
View Solution25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
View Solution18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?View Solution3 men and 5 women together can complete a work in 6 days, whereas 4 men and 9 women together can doit in 4 days. How many women are required to do the same work in 7 days?
View Solution4 men and 10 women can complete 13 is part of work in 4 days. Now, 2 more men and 2 women joined the work and 29 additional work is completed in 2 days. If remaining work is to be completed in 3 days, then how many more women should join the work?
View Solution